Permit: T10CM02212
Permit Details
Apply Date:
08/11/2010
Applicant:
N/A
Description:
NEW: CONVENIENCE STORE
Architects:
- ERIN LOUDERMILK
Contractors:
- THATEN CONSTRUCTION INC
Permit Reviews
Permit Number - T10CM02212
Permit Status: C of o
Permit Description: NEW: CONVENIENCE STORE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/28/2011 | REVISION - SITE | 01/28/2011 | COMPLETED |
| 02/16/2011 | REVISION - - 1ST | 02/16/2011 | COMPLETED |
| 02/16/2011 | REVISION - - 1ST | 03/03/2011 | COMPLETED |
| 08/11/2010 | PLANS OK TO SUBMIT - COMM | 08/11/2010 | COMPLETED |
| 08/11/2010 | PLANS OK TO SUBMIT - SITE | 08/11/2010 | COMPLETED |
| 08/11/2010 | COMMERCIAL NEW | 10/01/2010 | COMPLETED |
| 08/11/2010 | SITE | 10/01/2010 | COMPLETED |
| 10/01/2010 | RESUBMITTAL | 12/02/2010 | COMPLETED |
| 10/01/2010 | RESUBMITTAL - SITE ALL | 11/04/2010 | COMPLETED |
| 11/04/2010 | REVISION - SITE | 12/15/2010 | COMPLETED |
| 12/02/2010 | RESUBMITTAL | 12/06/2010 | COMPLETED |
| 12/06/2010 | RESUBMITTAL | 12/15/2010 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM02212
Permit Description: NEW: CONVENIENCE STORE
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/10/2011 | ELECTRIC - UFER | GDABBS | Approved | IVRS - Inspection :* |
| 02/25/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) PER LETTER FROM KIRCK HOFFMAN ENGINEER FOR INTECH GROUP |
| 02/25/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 03/01/2011 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
| 03/10/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 03/15/2011 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* 1) CORRECTIONS FROM 3/11/11 INSPECTION COMPLETED |
| 03/15/2011 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* |
| 03/22/2011 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 03/22/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 03/23/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
| 03/23/2011 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* |
| 04/06/2011 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | IVRS - Inspection :* |
| 04/07/2011 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 04/13/2011 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) FUEL CANOPY COLUMNS |
| 04/13/2011 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 04/18/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/20/2011 | FRAMING | MHENSON | Approved | IVRS - Inspection :* APPROVED NOT TILES UNTIL TRADE INSPECTORS OKAY |
| 04/20/2011 | FIRE - FINAL | DRamirez | Approved | Approved 4/20/11 |
| 04/20/2011 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 04/20/2011 | NPPO - FINAL | JFEMLING | Approved | Approved |
| 04/20/2011 | FIRE - FINAL | DSIWARSKI | Approved | Not ready for CofO inspection. |
| 04/22/2011 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 04/22/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 04/25/2011 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) RECEIVED LETTER OF TORQUE AND SECONDARY REVISION 2) CONTRACTOR TO LOCK OUT TAG OUT 3) #4 DISPENSOR HAS UNIONS |
| 04/25/2011 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
| 04/25/2011 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 04/25/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 04/26/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 04/26/2011 | FIRE - HYDRANTS | DRamirez | Approved | Approved 4/20/11 |
| 04/27/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 04/27/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/28/2011 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | |
| 04/29/2011 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | |
| 04/29/2011 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | |
| 04/29/2011 | ELECTRIC - PROGRESS | DSANTACR | Approved | |
| 04/29/2011 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 04/29/2011 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/29/2011 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/29/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 05/02/2011 | LANDSCAPE - FINAL | RDLD | Approved | |
| 05/04/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 05/05/2011 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 05/05/2011 | SIGN - FINAL | JYBARRA | Approved | |
| 05/05/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | |
| 05/05/2011 | BUILDING - FINAL | GDABBS | Approved | |
| 05/05/2011 | CERTIFICATE OF OCCUPANCY | GDABBS | Approved |