Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T10CM01889
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/15/2010 | MARTIN BROWN | FIRE | REVIEW | Denied | Fire access lanes required to be 20 wide unobstructed. The islands on the NW turn around appear to impinge on the 20'. Fire Department approved lock boxes will be needed at gates. No Parking - Fire Lane signs will be needed. Sign detail on page x1.3 is incorrect. Exiting diagrams are confusing (sheet g1.8). Sometimes exit numbers seem to exceed 50, but panic hardware is not provided. Door swings may be incorrect. It appears there is a stove in kitchen. This would require a type 1 hood, with suppression system. |
| 09/20/2010 | GERRY KOZIOL | WWM | REVIEW | Denied | 1. NEED CAPSITY EVALUATION BY 3RD FLOOR PUBLIC WORKS BLDG - KURT STEMM 740-660 2. NEEDS PCRQRD REVIEW OF LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER - BY PCRWRD 1ST FLOOR PUBLIC WORKS BLDG - ROY MONTOYA'S GROUP. 3. NEED A COPY OF PRIVATE SEWER TO 8TH FLOOR BASE MAP UPDATE. 4. NEED PDEQ1 APPROVAL FOR PRIVATE ON SITE SEWER. BANK OF AMER. BLDG 7TH FLOOR - DAVID AMISH 743-7400 5. COMMUNITY BLDG #6 |
| 09/20/2010 | MATT FLICK | ENGINEERING | REVIEW | Completed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/12/2010 | CPIERCE1 | OUT TO CUSTOMER | Completed |