Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - GRADING ALL
Permit Number - T10BU01437
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/22/2010 | LAITH ALSHAMI | ENGINEERING | REVIEW | Denied | Laith Alshami, Engineering and Floodplain Review, 11/22/2010 Mission Rose Academy Grading Plan Comments: 1- The building wall is touching the 100' erosion hazard setback. Since the structure foundation usually extends outside the footprint of the building, it is safe to assume that the foundation will be within the erosion hazard setback which might undermine the foundation and consequently at least part of the structure in case the 100-year erosion occurs. Address this issue and propose a way to protect the building from erosion. 2- The Apostolic Church development encountered soil piping problems during construction. It is very likely that this project may encounter the same problem. It does not appear that the geotechnical report has not addressed this issue which might cause some concerns during and after construction. The geotechnical report shall propose remedies for the problem if necessary. If you have any questions, I can be reached at 837-4933 or Laith.Alshami@tucsonaz.gov |
| 11/29/2010 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | November 29, 2010 Development Services Department Zoning Review Section Michael St.Paul Planning Technician T10BU01437 Grading Plans for D09-0038 Address: 1690 W. Irvington Rd. Comments: 1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Please submit one copy of the approved and stamped Development Plan, Landscape, and NPPO plans with the next grading plan submittal. 3. Zoning will re-review the grading plan on the next submittal to ensure compliance with the approved development plan. Additional comments may be forthcoming. |
| 12/01/2010 | ANDREW CONNOR | NPPO | REVIEW | Approv-Cond |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 12/02/2010 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |