Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA SUBMITTAL
Plan Number - T09PI00014
Review Name: PIA SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | COT STREETS DIVISION | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | COX COMMUNICATION | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Approved | |
08/27/2009 | RLEIGH1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Approved | |
09/01/2009 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | Comments on pg 10 & 11 (2nd subm.) Pg 10. minimum 24" RCP due to clean up equipment operated by City. Pg 11. show the toe down for drainage outlet. |
09/15/2009 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Approv-Cond | Provide floodplain use permit number and delineate any proposed irrigation line easements prior to submitting mylars. |
09/16/2009 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | September 16, 2009 ACTIVITY NUMBER: T09PI00014 PROJECT NAME: Sunnyside Pointe PROJECT ADDRESS: 5145 S 1st Avenue PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. Many redlines from the original set were not addressed. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
09/17/2009 | RICHARD LEIGH | PIA COORDINATOR | OUT TO CUSTOMER | Completed | Please submit Utility Receipt from Tucson Water |
09/18/2009 | RICHARD LEIGH | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | Please submit Utility Receipt from Tucson Water |
10/14/2009 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approv-Cond | NPPO stamped approved plans were received. Thank you.Until the legal easements are completed, I can only give you a approved con. |