Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T08BU00996
Parcel: 133033000

Review Status: Completed

Review Details: RESUBMITTAL - GRADING ALL

Permit Number - T08BU00996
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/19/2008 LOREN MAKUS ENGINEERING REVIEW Denied September 26, 2008
T08BU00996
Grading Review
Address each of the following comments. Include a letter explaining how each comment is addressed. Note that additional comments may be forthcoming.

1. As previously commented, check all of the references to details to ensure that they are correctly directed. Check and revise all references as necessary.
2. As previously commented, provide a geotechnical report that properly describes this project site.
3. As previously commented, use the checklist that ADEQ has provided to meet the requirements of the permit issued in February of this year. The checklist enclosed in the front of the SWPPP is not the updated checklist.
4. Specifically identify the operator who has operational control over plans and specifications and specifically identify the operator with operational control over day to day operations. Also identify the specific parties responsible for all activities required to maintain compliance with the SWPPP and the general permit. Where information about operators is not known, leave spaces for the information to be added later.
5.
If you have questions or wish to set up a meeting please contact me at loren.makus@tucsonaz.gov

Loren Makus
Senior Engineering Associate
09/19/2008 DAVID RIVERA ZONING REVIEW Denied 09/19/2008

Development Services Department
Zoning Review Section

David Rivera
Principal Planner

Comments:

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan at this time.

2. While zoning acknowledges that the grading plan is in substantial zoning compliance as it relates to the Zoning review purview, with the unapproved version of the development plan, the grading plan cannot be approved at this time. Please review the grading plan and compare it to the most current version of the development plan to ensure accuracy and to ensure that any revisions that have been made to the development plan after the grading plan was submitted are addressed.

3. Please ensure that the grading plan matches the CDRC approved and stamped development plan. Zoning will re-review the grading plan on the next submittal to ensure compliance with the CDRC approved and stamped development plan.
09/29/2008 ANDREW CONNOR NPPO REVIEW Denied Submit a copy of the approved development plan including landscape and native plant preservation plans for reference. The grading application will be reviewed for compliance when the approved documents are included in the submittal. Revise grading plans as necessary to comply with the approved documents.

Ensure that all Engineering comments and concerns are addressed.

Final Status

Task End Date Reviewer's Name Type of Review Description
09/30/2008 CINDY AGUILAR OUT TO CUSTOMER Completed
09/30/2008 SUE REEVES REJECT SHELF Completed