Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T07CM00308
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/07/2007 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 06/21/2007 | TERRY STEVENS | ZONING | REVIEW | Denied | 06/22/07 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 06/29/2007 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Revise the outside air calculations to provide ventilation for the kitchen. (Note: correct the areas to correspond to the room sizes shown on the plans.) Reference Sections 403.3 and 403.3.2, IMC 2003. 2. Clarify the capacity of the rooftop AC unit; 5 tons or 6 tons? |
| 06/29/2007 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Revise the location of the flow control device so that no vent is located between the grease trap and the flow control device. Section 1014.3, UPC 2003. |
| 07/03/2007 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | Approved site plan is required prior to building plan approval. |
| 07/06/2007 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 07/18/2007 | CHRIS KIEL (WILDAN) | BUILDING-COMMERCIAL | REVIEW | Denied | 1) Door swings for restrooms shall swing in therefore does not encroach on maneuvering clearance required to open door per Chapt. 4 ANSI A117.1 2003. COMMENT REMAINS: Provide the required maneuvering clearance on the pull side of the accessible restroom doors per section 404.2.3 of ANSI 117.1-2003. The current submittal shows the water closet within the maneuvering clearance. COMMENT REMAINS: The current submittal for the men's and women's restrooms still fail to provide the required maneuvering clearance on the pull side of both the men's and women's restroom doors in accordance with section 404.2.3 of ANSI 117.1-2003 as the water closets are located within the required area. Please revise accordingly. In addition, if the doors are required to have closers by another department (i.e health department), then the hallway width will have to be increased to 4'-0" per section 404.2.3. 2) Provide cost breakdown on the plans per 2003 IBC section 3409.6 to justify 20% cost of construction. COMMENT REMAINS: Please revise the project cost calculation regarding the justification of the 20% expense per section 106.1.1 of the 2003 IBC to remove the costs associated with the installation of the drinking fountain since it is not going to be installed per the submitted variance and associated plans. In addition, please provide verification regarding the listed cost of the handicap table per section 106.1.1. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 07/18/2007 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |
| 07/18/2007 | CINDY AGUILAR | REJECT SHELF | Completed |