Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T07CM00308
Parcel: 10612149A

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T07CM00308
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/29/2007 DAVE MANN FIRE REVIEW Approved
01/31/2007 BETSY COTTLE COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
02/06/2007 TERRY STEVENS ZONING REVIEW Denied 02/09/07

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:


1. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal.

2. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming.
02/09/2007 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov
IF YOU CARE TO DISCUSS.

1. Electrical plans call for MUA-1 on MUA Diagram Sheet E2.0. Is line-to-line on Electrical, 3-phase on Mechanical Sheet M1.0. Coordinate with Mechanical and clarify.
2. Provide conductor size for the unit above.
3. Provide an electrical circuit for H-1. Reference Sheet M1.0.
4. Provide electrical circuits for EH-1 and EH-2.
5. Demonstrate compliance with the Tucson Lighting Code, http://www.tucsonaz.gov/dsd/Codes___Ordinances/Tucson_Lighting_Code.pdf.
6. Provide cut sheets for all exterior lighting fixtures.
7. Electrical load on B-8 appears to be 720 VA, not 180, so the load on Phase B of that panel would be 3540 VA, not 3000. Ice Machine appears to be 1800 VA if the Equipment Schedule on Sheet A2.0 is accurate. So Phase B on Panel a is 24,634 VA, or 205 A, which overloads the panel, feeder, and service.
02/13/2007 GERRY KOZIOL WWM REVIEW Denied NEEDS 8TH FLOOR CREDIT EVALUATION-740-6500
02/22/2007 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Revise the natural gas piping design to include all of the gas-fired equipment (e.g. AC-1). If the water heater is gas-fired, provide the equipment specifications and include it in the gas piping design; the unit does not appear to have electric power provided to it. Reference Sections 103.2.3 and 1209.1, UPC 2003.
2. Provide the minimum plumbing facilities required by Table 2902.1, IBC 2003, for assembly (A-2) occupancy (e.g. a service sink).
3. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference Section 414.1, UPC 2003 and Section 804.3, IECC 2003.
4. Provide floor drains in the kitchen areas. Reference Sections 412.2.2 and 704.3, UPC 2003.
5. Provide access and working space for the water heater. Reference Section 306.1, IFGC 2003.
6. Provide a detail of the water heater installation, including the excess pressure relief, expansion tank, and valves. Reference Sections 103.2.3, 605.5, and 608.3 UPC 2003.
7. Appliances to be directly connected to the water supply system that do not have listed, integral backflow preventers or integral air gaps may require reduced pressure principle backflow preventers. Please submit equipment sheets for determination. Reference Section 603.0, UPC 2003.
8. Provide CW shut off valves for each building entrance. Reference Section 605.2, UPC 2003.
9. Clarify the waste connections for sink P3 and coordinate the plumbing plan with the waste and vent diagram. Reference Section 103.2.3, UPC 2003.
10. Provide a waste and vent diagram for the new restroom. Reference Section 103.2.3, UPC 2003.
11. Provide an upper terminal cleanout for the lavatory in the new restroom. Reference Section 707.4, UPC 2003.
12. Provide an additional cleanout for the building drain for the new restroom. Reference Section 707.5, UPC 2003.
13. Provide specifications for the icemaker. If the unit requires a minimum inlet pressure greater than 15 PSI, adjust the water pressure calculations and pipe sizing as appropriate. Reference Section 608.1, UPC 2003.
14. Provide the size of the existing water meter, the size of the existing water service pipe, and the total demand (existing plus new) on the water meter. Reference Section 610.0, UPC 2003.
15. The use of a shower as an indirect waste receptor is not allowed. Reference Section 804.1, UPC 2003.
16. Clarify the connection of the hand sink (P6) referenced in keynote 18. Reference Section 103.2.3, UPC 2003.
17. Provide specifications for the grease interceptor and show that it has been installed in accordance with the manufacturer's recommendations and Section 1014.0, UPC 2003. Reference Section 103.2.3, UPC 2003.
02/22/2007 ROBERT SHERRY WATER REVIEW Denied Show the location and the size of both the water meter and the reduced pressure backflow preventer assembly. Reference Section 103.2.3, UPC 2003.
02/22/2007 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Revise the font size used on the drawings to a minimum of 1/8-inch (all upper case). Reference Section 302.3, Uniform Administrative Code, 1997.
2. Provide manufacturer's equipment data along with mechanical and electrical operating information for the new exhaust fan in the new restroom. Reference Sections 301.6, 403.2.1 and 403.3, IMC 2003.
3. Specify the exhaust flow rate for each of the restroom exhaust fans. Ventilation for restrooms in public spaces requires a minimum of 75 CFM of mechanical exhaust per water closet or urinal. Reference Table 403.3, IMC 2003.
4. Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the roof top units, EF-1, AC-1 and EC-1, the electric unit heaters, and the new hood, EH-1. The weight of AC-1 is scheduled as 700 pounds, not 150 pounds as noted on the structural drawing and the operating weight of an Arctic Circle ED-430 is 260 pounds, not 140 pounds. Reference Sections 302.1 and 507.6, IMC 2003.
5. Coordinate the support details for the support of the hood, EH-1. Note that the hood requires a clearance of 18" from combustible materials. Reference Sections 507.6 and 507.9, IMC 2003.
6. Show that the design of the walls adjacent to the Type I hood comply with Section 507.9, IMC 2003.
7. Show how the portion of the Type I hood penetrating the ceiling complies with the requirements of Section 506.3.10, IMC 2003. Reference Section 507.10, IMC 2003.
8. Show that the location of the hood exhaust fan complies with the requirements of Sections 304.1, 304.10, 506.3.12.3, and 506.5.5, IMC 2003.
9. Show how the specified electric heaters are capable of maintaining a minimum temperature of 68°F in the interior spaces intended for occupancy on a design heating day (32°F). Reference Sections 309.1 and 312.1, IMC 2003.
10. Show the size, routing, and termination of the condensate drains. Reference Section 307.2, IMC 2003 and Section 807.2, UPC 2003.
11. Show that a separation of at least ten feet exists between air intake openings and exhaust openings. Reference 401.5, IMC 2003.
12. Provide calculations to show that the common ventilation system is sized in accordance with Section 403.3.2, IMC 2003.
13. Show the size of the grease exhaust duct. Reference Sections 106.3.1 and 506.3.4, IMC 2003.
14. Provide information to show how the "grease trough, curb, and cap" shown in detail 1/M2.0 complies with the requirements of Section 506.5.2, IMC 2003.
15. Provide a design and structural calculations to show that the spiral duct (see detail 4/M2.0) is supported adequately. Reference Sections 105.0 and 603.10, IMC 2003.
02/26/2007 CHRISTY FOREMAN BUILDING-COMMERCIAL REVIEW Denied CITY OF TUCSON DEVELOPMENT SERVICES
STRUCTURAL REVIEW COMMENTS

DATE: 3/1/07
ACTIVITY NUMBER: T07CM00308
PROJECT NAME: Snow cones and Taco
PROJECT ADDRESS: 3235 N. Flowing Wells
ARCHITECT / ENGINEER: Arch West
PROJECT REVIEWER: Christy Foreman


TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1108 OR EMAIL AT CHRISTY.FOREMA1@TUCSONAZ.GOV IF YOU CARE TO DISCUSS.

1) Provide structural calculations to verify that the existing calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the roof top units, EF-1, AC-1, EC-1, electric unit heaters, and the new hood EH-1.
2) Provide details for attachment / support of the hood.
3) Provide drinking fountain per table 2902.1 per IBC 2003. Drinking fountain spout heights and water flow per ANSI A117.1 2003 602.4 and 602.6.
4) Per last permit 1995 CPES Facility it appears the shower was added without permits.
5) Per last permit it appears covered porch to North was not permitted. Provide details and structural calculations.
6) Appears additional area has been added to west canopy. Provide details and structural calculations.
7) It appears additional canopy / façade has been added to the east Side of building.
8) Per last permit sink and door relocated on men's restroom.
9) Per last permit wall between kitchen and open area is a new wall.
10) Door swings for restroom's shall swing in therefore does not encroach on maneuvering clearance required to open door per Chapt. 4 Ansi A117.1 2003.
11) Provide cost breakdown per 2003 IBC section 3409.6 to justify 20% cost of construction.
03/01/2007 PATRICIA GILBERT ENGINEERING REVIEW Denied An approved site plan is required prior to building plan approval. Once the site plan is approved by all reviewing sections the building plan can be approved.

Final Status

Task End Date Reviewer's Name Type of Review Description
03/12/2007 GERARDO BONILLA OUT TO CUSTOMER Completed
03/12/2007 SUE REEVES REJECT SHELF Completed