Plan Review Detail
Review Status: Completed
Review Details: PIA SUBMITTAL
Plan Number - T06PI00041
Review Name: PIA SUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/08/2006 | TAMI HAUSER | ENGINEERING | REVIEW | Needs Review | |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | COX COMMUNICATION | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/08/2006 | TAMI HAUSER | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | SUBMIT UTILITY CLEARANCE LETTERS |
| 08/21/2006 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approved | |
| 08/29/2006 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Please submit your approved NPPO Site Plan. The ROW area should have been included. If it was not included under the site inventory, then it must be addressed now. |
| 09/01/2006 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed these plans and have the following comments: 1. Sheet 2 - Note 11 - Curb Acess Ramps need to have truncated domes instead of tactile grooves. 2. Sheet 3 - What will be the pavement section? How much asphalt over how much aggregate base? No further comments. 9/1/01 |
| 09/07/2006 | Estevan Tineo | DOT ENGINEERING | REVIEW | Denied | T06PI00041 (Sunnyside Elementary School) 1. Sheet 1 of 3: Add the following note: A soils Engineer shall conduct Quality Control material and inspection testing in accordance to City Standards and Specifications. 2. Sheet 1 of 3: Note 28 is note needed, please remove. 3. Sheet 2 of 3: Are the ramps indicated on the west side of Sun View Way existing or proposed ramps? 4. Sheet 2 of 3: The proposed sewer should be public. 5. Sheet 2 of 3: I suggest mid-block ramps at about station 4+60. 6. Sheet 3 of 3: Detail 1 of 3: Call out stationing (from station to station) for proposed roadway section. 7. Is the proposed improvements in existing public r/w? If so, then add recordation information. However, if this r/w to be dedicated then add Book and Page on the first sheet under the project title. 8. Sheet 3 of 3: Detail 1 of 3: Indicate 2% nominal sidewalk cross slope for both sides of the roadway. In addition, indicate a control joint between the sidewalk in the r/w and on private property. 9. Sheet 3 of 3: Indicate roadway section. 10. Sheet 3 of 3: Detail 2/3: Call out Detail 205, type 2 scupper. In addition, call new rip-rap and filter fabric. |
| 09/14/2006 | TAMI HAUSER | PIA COORDINATOR | CUSTOMER CALLED | Completed | |
| 09/14/2006 | TAMI HAUSER | PIA COORDINATOR | OUT TO CUSTOMER | Completed |