Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T06CM03000
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/09/2006 | BETSY COTTLE | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
| 08/09/2006 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide information to show that backflow protection is not required for this project. Reference Section 27-75, COT Ordinance 9976. |
| 08/09/2006 | MARTIN BROWN | FIRE | REVIEW | Denied | Fire sprinklers required. Please add the following automatic sprinkler criteria to the plans: 1. The hazard classification of the occupancy including any special hazards. 2. The design standard to be used. 3. The availability and adequacy of the water supply (flow data) 4. The design density and the area of operation. |
| 08/10/2006 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 08/14/2006 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | The site plan must be approved before the Building Permit can be approved. Include a copy of the approved site plan with the Building Permit application. |
| 08/25/2006 | SREEVES1 | ZONING | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/25/2006 | JMORALE1 | OUT TO CUSTOMER | Completed |
| 08/25/2006 | JMORALE1 | REJECT SHELF | Completed |