Permit Number: T06CM00288
Parcel: 141185330

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T06CM00288
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/11/2006 ROBERT SHERRY WATER REVIEW Denied 1. Revise the site drawing to show the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference Section 103.2.3, UPC 2003.
2. Provide equipment data for the reduced pressure backflow preventer assembly. Reference Section 103.2.3, UPC 2003.
10/12/2006 STEVE SHIELDS ZONING REVIEW Denied 10/12/06

Development Services Department
Zoning Review Section

Steve Shields
Lead Planner

Comments: T06CM00288 - Building plan review

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped site/development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.

4. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development plan stamped for site plan approval and signatures is required before the building plan can be approved by Zoning. Two copies of the approved site/development plan, landscape and NPPO plans are to be submitted with the building plans packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. The development plan may be walked through for stamps and site card sign off. Submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the site plans packet processed together for site approval.

If you have any questions about this transmittal, please call Steve Shields,
(520) 791-5608 ext. 1180.

C:\planning\building\t06cm00288.doc
10/12/2006 DAVE MANN FIRE REVIEW Denied ) Please add the following automatic sprinkler criteria to the plans:
a. The hazard classification of the occupancy including any special hazards.
b. The design standard to be used.
c. The availability and adequacy of the water supply.
d. The design density and the area of operation. (Flow Data)
2) Backflow preventer on Fire Service not allowed. Please remove from plans.
3) Please provide designation of occupancy classifications for various areas of the building.
4) Fire Department Lock box required at entrance gate. Include location on plans. (Application form has been included in plans)
5) Be aware that separate permits will be required for fire sprinklers, fire sprinkler underground piping, fuel tank installation, and fire alarms.

Page C6A is missing.
10/16/2006 GERRY KOZIOL WWM REVIEW Denied need 8th floor review of connection/method to public sewer.
10/16/2006 BETSY COTTLE COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed No development plan/site plan completed within the deadline dates.
Southeastern District
18,325 sf $18,732.34
10/16/2006 PAUL MACHADO ENGINEERING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
10/20/2006 SUE REEVES OUT TO CUSTOMER Completed
10/20/2006 SUE REEVES REJECT SHELF Completed