Permit Number: T06BU00873
Parcel: 13413057F

Address:
51 S PANTANO RD

Review Status: Completed

Review Details: GRADING

Permit Number - T06BU00873
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/27/2006 ANDREW CONNOR NPPO REVIEW Denied Site plan approval is necessary to continue review.
05/18/2006 LOREN MAKUS ENGINEERING REVIEW Denied May 18, 2006
Site and Grading Review: Furr's Cafeteria
T06CM02086 and T06BU00873
Loren Makus, E.I.T.

The site and grading plans for the propoesed Furr's Cafeteria at 51 S Pantano Road cannot be approved at this time. Since a complete drainage submittal was not provided with the site plan the plans cannot be approved at this time. Once a complete submittal is received, additional comments will be forthcoming. The following comments must be addressed:

1. Show location of driveway on each adjacent property. Driveways must be at least 80 feet apart on MS&R streets.. The measurement is taken at the point of tangency for the curb return.(Transportation Access Management Guidelines)
2. Provide a drainage report. The report must address detention and retention requirements. Five year threshold retention and detention requirements. Provide sufficient hydraulic analysis to demonstrate that all-weather access will be provided.
3. The Stormwater Pollution Prevention Plan for this project does not meet the minimum requirements of the ADEQ Construction General Permit. ADEQ provides a checklist for SWPPP preparation. The SWPPP checklist can be obtained from the ADEQ website at: http://www.azdeq.gov/environ/water/permits/download/cswppp.pdf. Include a completed SWPPP checklist with the SWPPP. In the checklist clearly describe the location within the SWPPP for each required element.
4. Show maneuverability for Solid Waste vehicle access to the compactor.
05/27/2006 DAVID RIVERA ZONING REVIEW Denied 05/27/06

Development Services Department
Zoning Review Section

David Rivera
Principal Planner

Comments:

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the grading plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal.

3. Zoning will re-review the grading plan on the next submittal to ensure compliance with the approved and stamped site plan. Additional comments may be forthcoming.

Final Status

Task End Date Reviewer's Name Type of Review Description
06/09/2006 SUE REEVES OUT TO CUSTOMER Completed
06/09/2006 SUE REEVES REJECT SHELF Completed