Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - GRADING
Permit Number - T04BU02156
Review Name: RESUBMITTAL - GRADING
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/26/2005 | Loren Makus | ENGINEERING | REVIEW | Denied | DATE: January 27, 2005 TO: Steve Whillier, Conestoga-Rovers and Associates SUBJECT: Site Plan: TIAA Superfund Site REVIEWER: Loren Makus ACTIVITY NUMBER: T04CM03976, T04BU02516 and T04OT01737 SUMMARY: The Site Plan and Grading Plan were reviewed by Development Services Department, Engineering Division on September 22, 2004. This review is only for the project parcels along Elvado Road, outside of the Tucson International Airport. The portion of the project within the Airport was reviewed for floodplain issues only. The Site Plan and Grading Plan were not approved for the Elvado Road parcels. Please address the following comments. 1. Clearly show the existing and proposed drainage patterns on the Elvado parcels. The TIA master drainage report and the City of Tucson TSMS study indicate that there is a significant discharge through the culverts under Nogales Highway. Label the discharge quantity on the site/grading plan. Discuss the disposition of the discharge in a drainage statement or drainage report. 2. Determine the 100-year water surface elevation and the extent of the City of Tucson floodplain for the discharge. Provide the supporting calculations in the drainage statement/report. 3. Provide details showing transition from the fill area to natural grade. Show that the toes of all fill slopes will be set back at least two feet from the property line. Revise the Site Plan, to address all of these comments and resubmit two copies of each for review. Include a letter explaining how each comment has been addressed. Loren Makus, E.I.T. Senior Engineering Associate Engineering Division Development Services |
| 02/07/2005 | DAVID RIVERA | ZONING | REVIEW | Denied | 02/07/05 Development Services Department Zoning Review Section David Rivera Senior Planner Comments: 1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering. Please insure that the grading plan matches the site plan. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/16/2005 | BETH GRANT | OUT TO CUSTOMER | Completed |