Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T02CM05314
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/13/2003 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Approved | |
| 02/19/2003 | BOB SUBA | ELECTRICAL-COMMERCIAL | REVIEW | Completed | Sheet E1 1. Indicate on plans that optional loads will be automatically shed if actual demand exceeds generator rating, if such is the case per the response letter of January 10, 2003. 2. Indicate on plans the information contained in Item 2 for sheet E1 in your response letter of January 10, 2003. Sheets E3, E11, E13, E15 1. Your response letter indicates the relocation/reuse of UL listed and labeled connectors. Please put this information on the plans. Sheet E6 1. Your response letter indicates that the RTU's disconnects come integral with the equipment. Per a conversation of February 21, 2003, the disconnects also come integral with the equipment. Please put this information on the plans. Sheet E8B 1. Provide weight and mounting detail for transformer T-6. This may have to go for structural review. |
| 02/24/2003 | MARTIN HAEBERLE | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 02/28/2003 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Sheet E1 1. Indicate on plans that optional loads will be automatically shed if actual demand exceeds generator rating, if such is the case per the response letter of January 10, 2003. 2. Indicate on plans the information contained in Item 2 for sheet E1 in your response letter of January 10, 2003. Sheets E3, E11, E13, E15 1. Your response letter indicates the relocation/reuse of UL listed and labeled connectors. Please put this information on the plans. Sheet E6 1. Your response letter indicates that the RTU's disconnects come integral with the equipment. Per a conversation of February 21, 2003, the disconnects also come integral with the equipment. Please put this information on the plans. Sheet E8B 1. Provide weight and mounting detail for transformer T-6. This may have to go for structural review. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/03/2003 | LISA LESNY | OUT TO CUSTOMER | Completed |