Permit Number: DP21-0170
Parcel: 13413057R

Review Status: Completed

Review Details: DEV PKG - RESUBMITTAL

Permit Number - DP21-0170
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/05/2021 SBEASLE1 START PLANS SUBMITTED Completed
10/06/2021 SBEASLE1 COT NON-DSD TRAFFIC Reqs Change Email from: David.Stiffey@TucsonAz.gov
To: CDRC
Wed 10/6/2021 1:37 PM

1. P.A.G. 206 standard driveway apron is possible with wedge curb and needs to be installed at this location. New pavement tie-in at Sherwood Village Dr. needs to meet P.A.G. standard 206.


David Stiffey
City of Tucson
Transportation and Mobility
10/25/2021 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Take Five Oil Change Facility – 7970 E Broadway Blvd
Development Package (2nd Review)
DP21-0170

TRANSMITTAL DATE: October 25, 2021

DUE DATE: October 29, 2021

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is June 27, 2022.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

1. This comment shall be addressed prior to approval of the DP. COMMENT: 2-06.4.9.E – Either a lot combination will be required or some type of cross access easement or agreement will need to be recorded.

2. Provide either a note on the plan or detail stating how this requirement will be met. COMMENT: 2-06.4.9.H.5.d – The plan and detail for the short-term bicycle parking does not address UDC Article 7.4.9.B.1.e.

3. This comment shall be addressed prior to approval of the DP. COMMENT: 2-06.4.9.L – Some type of cross access easement or agreement will need to be recorded for the access proposed along the southern portion of the site. Provide the recordation information on the plan.

Once comment 2 is addressed Zoning will put a hold on the C of O for T21CM05319 until documentation for the cross access is provided.

If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov.

To resubmit your plans for additional review, please visit: https://docs.tucsonaz.gov/Forms/tucsonpermitapp

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
10/27/2021 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
10/29/2021 SBLOOD1 ENGINEERING REVIEW Reqs Change 1. See previous comment 2 - Still don't see the address and phone number of the firm who prepared the report. It all should be provided on the cover sheet as per Admin Manual section 2-06.4.1 The name, mailing and email addresses, and phone number of the primary property owner of the site, the developer of the project, registrant(s), and other person(s), firm(s), or organization(s) that prepared the development package documents shall be provided on the right half of the cover sheet. The applicable registration or license number shall be provided if prepared by or with the assistance of a registered professional, such as a surveyor, architect, landscape architect, or engineer. All sealing shall be consistent with Arizona Board of Technical Registration guidelines.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
11/08/2021 AWARNER1 LANDSCAPE REVIEW Approved
11/12/2021 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change Email from: COTDSDPermits
To: Linda Thompson
Fri 11/12/2021 3:18 PM

Returned for Corrections: DP21-0170

DESCRIPTION: Site/Grading/SWPPP - Take 5 Oil Change facility. 7960 E BROADWAY BL

Fee Balance: $0 (zero) Thank you for the payment.

SEE REVIEW COMMENTS and documents on PRO: www.tucsonaz.gov/pro
(If information is not available, check back later after data transfers to PRO.)
- Home page, Activity Search, enter the Activity/Permit Number
- Permits - click on blue tab to see different sections
- Reviews section - click on REVIEW DETAILS
- Documents section - click on VIEW

INCLUDE IN RESUBMITTAL
1) Comment Response Letter (your response to REQUIRES CHANGE comments)
2) Plan Set (all pages, full set, even if no changes were made)
3) Any other documents requested by review staff

Please title your THIRD submittal documents according to this example: 3_Comment Response Letter

FILEDROP for your Resubmittal
https://docs.tucsonaz.gov/Forms/tucsonpermitapp
- Select "Existing Application"
- In the "Permit Number" field, enter the number and, if applicable, any notes for our staff


Thank you.
Sharon Beasley, Building Permit Specialist

City of Tucson, Planning and Development Services
Email: COTDSDpermits@TucsonAz.gov
(disregard the email response that will be sent automatically)