Permit Number: DP19-0172
Parcel: 14039052F

Review Status: Completed

Review Details: DEV PKG - OK TO SUBMIT

Permit Number - DP19-0172
Review Name: DEV PKG - OK TO SUBMIT
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/19/2019 SBEASLE1 START PLANS SUBMITTED Completed
07/19/2019 SBEASLE1 PIMA COUNTY - ADDRESSING PIMA COUNTY - ADDRESSING Passed This project does not require review by Pima County Addressing.
Thank you
Nicholas Jordan, Addressing Specialist
Pima County Development Services Department
201 N Stone AV, Tucson, AZ 85701
(520) 724-9623
07/19/2019 SBEASLE1 WWM REVIEW Passed
07/19/2019 LOREN MAKUS ENGINEERING REVIEW Passed
07/22/2019 STEVE SHIELDS ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Steve Shields
Section Manager

PROJECT: Los Reales - Covered Parking with Solar
Development Package (1st Review)
DP19-0172

TRANSMITTAL DATE: July 22, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is July 21, 2020.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

2-06.4.9.H.5 - Per UDC Article 7.4.6.F.2.a.(1) Access lanes and PAALs must be setback at least one foot from an open structure, such as a carport or covered pedestrian access path as measured from the closest part of the structure or roof overhang. Provide the required 1'-0".

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov