Permit Number: DP18-0245
Parcel: 132130680

Review Status: Completed

Review Details: DEV PKG

Permit Number - DP18-0245
Review Name: DEV PKG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/03/2018 ALEXANDRA HINES START PLANS SUBMITTED Completed
10/03/2018 LIZA CASTILLO UTILITIES TUCSON ELECTRIC POWER Passed Agency notified for information only.
10/03/2018 ALEXANDRA HINES OTHER AGENCIES PIMA ASSN OF GOVTS Passed Agency notified for information only.
10/03/2018 ALEXANDRA HINES UTILITIES SOUTHWEST GAS Passed Agency notified for information only.
10/03/2018 ALEXANDRA HINES OTHER AGENCIES U. S. POST OFFICE Passed Agency notified for information only.
10/05/2018 NROSS1 OTHER AGENCIES TUCSON AIRPORT AUTHORITY Approved October 4, 2018

Alexandra Hines
Lead Planner
City of Tucson
Public Works Buildings – 201 North Stone Avenue
Tucson, AZ. 85701

RE: DP18-0245 The Bridges 150K SF Office / 1st Submittal, Received October 3, 2018

Dear Ms. Hines,

Thank you for the opportunity to comment on DP18-0245, The Bridges 150K SF Office; 1st Submittal, a development package application for an approximately 10.49 acre site, located south of the intersection of East 36th Street and South M L King Jr Way. The land use is PAD 15 (Planned Area Development 15) with the proposed development being an office use.

This site is within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace.

The Tucson Airport Authority has noticed two Tucson Airport Authority general notes, which would have been requested for this project submittal, have already been included on the general notes of the submitted plan. The Tucson Airport Authority is satisfied with the 1st submittal of this project and has no additional comments to submit.

Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811.

Respectfully,


Scott Robidoux,
Senior Airport Planner
10/23/2018 MASHFOR1 COT NON-DSD FIRE Approved INSTALLATION OF FIRE SERVICE UNDERGROUND SHALL
CONFORM TO NFPA 13. Deferred submittal shall be supplied to TFD for Sprinklers
10/25/2018 ZELIN CANCHOLA COT NON-DSD TRAFFIC Approved
10/30/2018 ANDREW CONNOR LANDSCAPE REVIEW Reqs Change ADMINISTRATIVE MANUAL
SECTION 2-10.0.0: LANDSCAPE PLAN REQUIREMENTS
4.1 Identification and Descriptive Data
A. All improvements and site information, such as adjacent rights-of-way and property lines, shown on the landscape plan will be identical in size and location to those shown on the base plan (site plan or tentative plat). Should amendments be required to the base plan through the review process, the same amendments will be made to the landscape plan which will then be resubmitted along with the base plan.
B. The landscape plan will contain the following identification in the lower right corner of each sheet:
Cross-reference to:
a. Rezoning case; PAD
f. Any other relevant case number for reviews or modifications that affect the site.
2-06.4.9.U - Indicate graphically, where possible, compliance with conditions of the revised PAD.
Ensure that all Zoning and Engineering comments and concerns are addressed.
Additional comments may apply.
10/31/2018 GLENN HICKS COT NON-DSD PARKS & RECREATION Approved No existing or proposed Tucson Parks and Recreation facilities are affected by this development.

Howard B. Dutt, RLA

Landscape Architect
Tucson Parks & Recreation
(520) 837-8040

Howard.Dutt@tucsonaz.gov
11/01/2018 EHAMBLI1 ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department, Plans Coordination Office

FROM: Elisa Hamblin, AICP; Lead Planner

PROJECT: The Bridges 150K SF Office, 2810 S MLK Jr. Way
Development Package (1st Review)
DP18-0245

TRANSMITTAL DATE: October 31, 2018
DUE DATE: October 31, 2018

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year expiration date is October 2, 2019.

1. 2-06.3.8 - The north arrow, contour interval, and scale as applicable to each sheet should be placed together in the upper right corner of each sheet. Revise landscape sheets to include this information in the upper right corner.

2. 2-06.4.3 - Include the assigned case number DP18-0245 adjacent to the title block.

3. 2-06.4.7.A.4 - Amend general note 3 on sheet 1 to identify the proposed use of the property as Administrative and Professional Office.

4. 2-06.4.9.H.5 - Provide PAAL width for the access lane to the north of the match line between sheets 5 and 6.

5. 2-06.4.9.H.5.c - Show all loading zones, vehicle maneuverability fully dimensioned, and access route. Clarify location of the two type A loading zones.

6. 2-06.4.9.Q - Provide the specific use proposed within the footprint of the building.

7. 2-06.4.9.W - Indicate the locations and types of proposed signs (wall, free-standing, pedestal) to assure there are no conflicts with other requirements and that minimal locational requirements can be met. Indicate if there are any existing billboards on site. Compliance to the Sign Code, Chapter 3 of the Tucson Code, is required.

8. Once the comments in this transmittal have been addressed and a new submittal received, please contact me if you wish to complete an expedited over-the-counter review.

If you have any questions about this transmittal, please contact me at Elisa.Hamblin@tucsonaz.gov or (520) 837-4966.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
11/01/2018 EHAMBLI1 ZONING HC REVIEW Approved
11/01/2018 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change For the building sewer on the southeast portion of the building, the rim elevation of the next upstream sanitary manhole (MH #9, 2475.31') is more than 12" below the first floor elevation (2477.40'). Do not provide a backwater valve. Reference: Section 715.1, IPC 2012, as amended by the City of Tucson.
11/02/2018 JOHN VAN WINKLE ENGINEERING REVIEW Reqs Change DP18-0245

1) Hydro report page 4 indicates that overflow drains in the water harvesting basins along the western edge of the property are 4" above the basin floors. Corresponding details on plan set sheet 7-8 indicate that basins 1-5 have a ponding depth is 9". Clarify if the inlets for the overflow drains allow for 9" of ponding depth or if ponding depth would be limited to 4" prior to entering the overflow drains
2) Provide top/bottom spot grades for all proposed water harvesting areas to show the effective ponding depth is maintained. Provide spot grades at the bottom of each inlet in addition to the spot grades shown at the top of the inlet as currently shown
3) Sheet 7 says to reference sheet 8 for pipe connection details. No details are shown on sheet 8. Provide a detail of the pipe connection to the existing catch basins, including method for basin cut-out and new pipe collar dowels or other joints. Similar to detail provided on Geico project. Pima County Regional Flood Control requests an inspection of this connection prior to final inspection or certificate of occupancy
4) Landscaping plans show several locations where tree trunks are out of line with parking stripes. Since this could interfere with the required vehicle overhang, adjust trunk locations so that they are shown as being in line with the parking stripes

John Van Winkle, P.E.
John.VanWinkle@tucsonaz.gov
520-837-5007
11/05/2018 JOHN BEALL COT NON-DSD COMMUNITY PLANNING Reqs Change Entitlements Section
John Beall

1. Applicant to provide letter of recommendation from DRC.
11/06/2018 ALEXANDRA HINES ZONING-DECISION LETTER REVIEW Reqs Change Plan Returned for Corrections (RFC) Notice: DP18-0245
Project Description: E SITE/GRADE/SWPPP - THE BRIDGES 150K SF OFFICE
To see review comments about the plans, please visit https://www.tucsonaz.gov/pro/pdsd/activity_search and enter activity number above.

This review has been completed and resubmittal is required. Prepare a Comment Response Letter which tells the reviewers what changes have been made to the plan and what comments are addressed. When you have made the necessary corrections to the plans, please resubmit the following items to PDSD Filedrop at https://www.tucsonaz.gov/file-upload-pdsd and the plans will re-enter the 20 working day review cycle:
1) Corrected plan set
2) Items requested by review staff

Please type the activity number in Project Description or Message of PDSD Filedrop for resubmittal. Please remember to name your files appropriately, for example: second (2nd) submittal,
2_plan_set.pdf
2_response_letter.pdf

The balance is $6143.10. Review fees must be paid prior to 2nd submittal review.

Alexandra Hines
11/06/2018 TOM MARTINEZ OTHER AGENCIES AZ DEPT TRANSPORTATION Reqs Change Regional Traffic Engineering has a question inquiring if there has been any updated data to the approved traffic documents and any additional impacts to the existing roadway network?

Please include any traffic documents in the next submittal or a response ADOT’s concerns. The proposed square footage of the development may affect the operations of the I-10 ramps adjacent to the overall site. Thank you

Tom Martinez <TMartinez@azdot.gov>

Final Status

Task End Date Reviewer's Name Type of Review Description
11/06/2018 AHINES2 OUT TO CUSTOMER Completed