Permit Review Detail
Review Status: Completed
Review Details: DEV PKG - RESUBMITTAL
Permit Number - DP18-0043
Review Name: DEV PKG - RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/04/2018 | KELLY LEE | START | PLANS SUBMITTED | Completed | |
| 05/15/2018 | MARTIN BROWN | COT NON-DSD | FIRE | Approved | |
| 05/17/2018 | DAVID RIVERA | ZONING HC | REVIEW | Approved | |
| 05/17/2018 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: David Rivera PDSD Zoning Review Section PROJECT: The Prime Leaf Dispensary - 1525 N Park Avenue - C-2 Zoning Development Package (2nd Review) DP18-0043 - New MM Dispensary Location TRANSMITTAL DATE: May 17, 2018 DUE DATE: June 4, 2018 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is February 14, 2019. SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS) Section 1. FOLLOW UP TO PREVIOUS COMMENT 15: Add the one way note and arrow to the one way drive lane around the west and south sides of the building. 2-06.4.9.H.5 - If utilizing parking area access lanes (PAALs), they shall be designed in accordance with Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC. PREVIOUS COMMENT 15: Remove any reference to a drive-through use. The city of Tucson Ordinance does not allow for a drive-through for Medical Marijuana Dispensary uses, see UDC section 4.9.9.E.1.f. It is wide enough to be used as a one-way access lane if needed. If the access lane is retained as depicted on the DP a full four foot wide sidewalk adjacent to the building is required. The APC containers will have to be relocated in order to have a continuous sidewalk. If the access lane will not be constructed provide barriers to keep vehicles from accessing the area. (The access lane width requirements are as follows; min. 10' travel lane, four foot wide sidewalk, 2 foot setback from property line, 16 foot total width. 2. FOLLOW UP TO PREVIOUS COMMENT 16: List within the building footprint the use of the building "MM Disp." 2-06.4.9.Q - Provide the square footage and the height of each commercial, industrial, or business structure and the specific use proposed within the footprint of the building(s). PREVIOUS COMMENT 16: Clarify if the overall height is based on a pitched design with an all-around exterior wall height of 12 feet? Include a copy of the building elevations with the next submittal of the DP. 3. Comment: Because this was an E-Plan submittal and no hard copy was provided I cannot review and approve the revisions over the counter. If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields any time during the week at (520) 837-4956 or email Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 05/29/2018 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Completed | |
| 05/31/2018 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Approved | |
| 05/31/2018 | ANDREW CONNOR | LANDSCAPE | REVIEW | Approved | |
| 06/08/2018 | ALEXANDRA HINES | ZONING-DECISION LETTER | REVIEW | Reqs Change | Resubmit package to address reviewer comments. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/08/2018 | AHINES2 | OUT TO CUSTOMER | Completed |