Permit Review Detail
Review Status: Completed
Review Details: REVISION - DEV PLAN
Permit Number - D08-0004
Review Name: REVISION - DEV PLAN
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/30/2009 | FERNE RODRIGUEZ | START | PLANS SUBMITTED | Completed | |
09/30/2009 | JOE LINVILLE | LANDSCAPE | REVIEW | Approved | |
09/30/2009 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | September 9, 2009 The Engineering Division recommends approval of the revised development plan. |
09/30/2009 | JWILLIA4 | ZONING-DECISION LETTER | REVIEW | Approv-Cond | COMMUNITY DESIGN REVIEW COMMITTEE DEVELOPMENT SERVICES September 10, 2009 Triumph Builders Southwest LLC 3450 S Broadmont Dr #11 Tucson, Arizona 85713 Subject: D08-0004 TPC @ Gateway Center Development Plan Dear Triumph Builders: The above referenced development plan has been CONDITIONALLY APPROVED by the Community Design Review Committee. Please submit the following documents for sign-off. 1 Rolled blueline COMPLETE SET of the Development Plan, Landscape Plan, and the Native Plant Preservation Plan (if part of the original submittal). Please include applicable sheets from any other concurrent reviews. AND 1 Rolled blueline set of the Development Plan. AND 1 CD that contains all of the drainage/hydrology and other reports submitted for the review and approval of this plan. The extra rolled blueline set that you submit will be delivered to Pima County for permanent recording. Additional blackline copies will be made from the complete set and distributed to various review agencies for their files. These copies will be ordered from the City's contracted print company and billed to you unless you already have an account at another printing company. Please let us know which printing company you would prefer to use and list them on your attached transmittal form when submitting your mylars to the CDRC office for sign-off approval. Your printing company will deliver the rolled blueline and two (2) blackline copies to your office. If you are out of town you will need to contact the printing company for pick up or mailing arrangement options. PLEASE HAVE THE CITY OF TUCSON APPROVAL STAMP PLACED ON EACH SHEET OF THE SUBMITTAL SET, PREFERABLY IN THE LOWER RIGHT HAND CORNER NEAR THE TITLE BLOCK. THE STAMP IS LOCATED AT http://www.tucsonaz.gov/dsd/CDRC___Rezoning/CDRC/CDRC_Stamp/cdrc_stamp.html. BLUELINE SETS THAT DO NOT HAVE THE STAMP WILL BE RETURNED FOR CORRECTION. Should you have any questions, please call me at 837-4919. Sincerely, John Williams Planning Technician All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/ Via fax: (520) 977-6369 |
09/30/2009 | ROGER HOWLETT | COT NON-DSD | COMMUNITY PLANNING | Approved | DEPARTMENT OF URBAN PLANNING & DESIGN COMMENTS Regarding SUBJECT: Community Design Review Committee Application CASE NUMBER: CASE NAME: DATE SENT D08-0004 TPC at Gateway Center 08/27/09 ( ) Tentative Plat ( X ) Revised Development Plan ( X ) Landscape Plan ( ) Revised Plan/Plat ( ) Board of Adjustment ( ) Other CROSS REFERENCE: NEIGHBORHOOD PLAN: Gateway Center PAD GATEWAY/SCENIC ROUTE: COMMENTS DUE BY: September 10, 2009 ( X ) Proposal Complies Plan Policies ( X ) No Resubmittal Required: However it should be noted that any future development for Lot 5, Block 3 of the Gateway Center will need to show that 182 parking spaces are being used to meet the required parking for 7333 E. Rosewood Street, Lot 2, Block 2. REVIEWER: JBeall 791-4505 DATE: 9/10/09 |
09/30/2009 | STEVE SHIELDS | ZONING | REVIEW | Denied | CDRC TRANSMITTAL TO: Planning & Development Services Department Plans Coordination Office FROM: Steve Shields Lead Planner PROJECT: TPC @ Gateway Center D08-0004 Development Plan - Revision TRANSMITTAL DATE: September 2, 2009 DUE DATE: September 10, 2009 COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1) D.S. 2-05.2.4.I & D.S. 2-05.2.4.N Clearly indicate (label) the location and height of the motorcycle parking canopy and provide setback dimensions on the plan. 2) I am willing to provide an over the counter review to ensure that the proposed motorcycle parking canopy meets setbacks. Call or mail to schedule an appointment 3) Additional comments may be forth coming depending on how each comment has been addressed. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956. C:\planning\cdrc\developmentplan\D08-0004dp.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan and additional requested documents. |