Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Record Request Details
Status:
Complete
Type:
Requests
Request Date:
10/06/2023
Requestor:
DOONE
Description:
**** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be
testing and cameraing the (3) new manholes that were
installed this summer with Pima County.
Duration of the work will be the following days:
9/25/23 from 5AM to 3PM
9/29/23 from 5AM to 3PM
10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day