Description:
We need to request a 90 day extension, due to the timeline and complexities of coordinating Desert Metal Works, Production schedule around the 480v Main Elect panel replacement on that building. We are trying to coordinate the shut down , when production schedule is lighter and less costly to the company, as this will take 2 days. We also have requested a power kill from TEP, but because of their lack of staffing and difficulty in communicating with them, it will make it additionally hard to coordinate a date. to replace Main 480v CT Panel