Plan Review Detail
Review Status: In Review
Review Details: TWPE 30% DESIGN REVIEW v.1
Plan Number - TW-PLAN-0526-0126
Review Name: TWPE 30% DESIGN REVIEW v.1
Review Status: In Review
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| TWPE System Planning | IN REVIEW | ||||
| TWPE Cathodic Protection | PENDING ASSIGNMENT | ||||
| TWPE Civil Engineers (CE) | PENDING ASSIGNMENT | ||||
| TWPE Engineering Manager Oversight | PENDING ASSIGNMENT | ||||
| TWPE Maintenance | PENDING ASSIGNMENT | ||||
| TWPE Survey | PENDING ASSIGNMENT | ||||
| TWPE Engineering Chief - Authorization | REVIEW COMPLETED | TW-PLAN-0526-0126 CMAR 2 – 16” WATER LINE REPLACEMENT - 30% review 1) W1: Use updated title block which has signature lines for Chief Engineer and Deputy Director sign off. 2) W1: Add EPL Plan Number TW-PLAN-0526-0126 3) W1: General alignment, why is the new pipeline so far to the southeast? A shorter route seems possible 4) W6: Any and all easements needed for this project must be recorded prior to TW sign off on plans. |
|||
| TWPE Project Managers | REVIEW COMPLETED | Resigned to Jeff Hancock | |||
| TWPE System Planning | REVIEW COMPLETED | No comments. A continuous 16" will remain, meeting hydraulic requirements. |