Review Status: Approved

Review Details: TWPE 60% DESIGN REVIEW v.1

Plan Number - TW-PLAN-0326-0016
Review Name: TWPE 60% DESIGN REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
TWPE Maintenance APPROVED
TWPE Operations APPROVED
TWPE Project Managers APPROVED
TWPE Project Supervisor Oversight APPROVED
TWPE Security APPROVED Camera's added per previous meeting. Readers installed at gates and doors
TWPE System Controls APPROVED Review markup and comments in Attachments.
TWPE Water Treatment APPROVED
TWPE Well Maintenance APPROVED Please see comment added 6/4 MF
TWPE Civil Engineers (CE) REVIEW COMPLETED HGL for wells needs to be clarified with System Planning and new HAs for well equipping need to be requested. Previous requests had inflow HGLs at 2400', these are as low as 2266. Z-013 would overproduce. We could pinch it back, but it would be better to equip correctly than waste the energy.
Additional markup was entered into bluebeam. Nothing of significance.
TWPE Electrical REVIEW COMPLETED
TWPE Instrumentation REVIEW COMPLETED Completed
TWPE Pipeline Protection REVIEW COMPLETED
TWPE Senior Engineering Associates (SEA) REVIEW COMPLETED Please see comments on sheets 20 and 22
TWPE System Planning REVIEW COMPLETED HGL for wells needs to be clarified with System Planning and new HAs for well equipping need to be requested. Previous requests had inflow HGLs at 2400', these are as low as 2266. Z-013 would overproduce. We could pinch it back, but it would be better to equip correctly than waste the energy. Additional markup was entered into bluebeam. Nothing of significance.