Plan Details

Status:
Awaiting submittal
Type:
TW CIP Planning & Engineering
Apply Date:
03/23/2026
Applicant:
Kara
Description:
NW Wells Treatment Facility - This project builds a 3.3 MGD PFAS/1-4 dioxane treatment facility to produce potable water from two contaminated wells (Z-013 & Z-014)
Architects:
  • Carollo Engineers
  • Kiewit
  • Tucson Water
  • Tucson Water Planning & Engineering
Contractors:

Plan Reviews

Plan Number - TW-PLAN-0326-0016
Plan Status: Awaiting Submittal
Plan Description: NW Wells Treatment Facility - This project builds a 3.3 MGD PFAS/1-4 dioxane treatment facility to produce potable water from two contaminated wells (Z-013 & Z-014)
Start Date Submittal Complete Date Status  
05/13/2026 TWPE 60% Design Review v.1 APPROVED Review Details