Permit Review Detail
Review Status: Approved
Review Details: RIGHT-OF-WAY REVIEW v.2
Permit Number - TR-UTL-0326-00595
Review Name: RIGHT-OF-WAY REVIEW v.2
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/17/2026 | Storm to Shade Review | PENDING ASSIGNMENT | All required information has been submitted for review in a timely manner, and the applicable conditions are included in the attachments. The Water Department did not complete their portion of the review; however, to prevent delays and avoid placing the permit on hold, Transportation has completed the review on their behalf with the appropriate conditions reflected on the permit. | ||
| 04/17/2026 | ROW Engineering Review - Standard | REVIEW COMPLETED | Review Complete and Approved with completion of the Associated Flood Use permit as noted. | ||
| 04/17/2026 | Transportation Application Review Express | REVIEW COMPLETED |