Permit Review Detail
Review Status: Requires Resubmit
Review Details: RIGHT-OF-WAY REVIEW v.3
Permit Number - TR-ROW-0426-00456
Review Name: RIGHT-OF-WAY REVIEW v.3
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/08/2026 | DTM Electrical - Standard | PENDING ASSIGNMENT | |||
| 05/08/2026 | MITZ District - Standard | PENDING ASSIGNMENT | |||
| 05/08/2026 | PIA Engineering Review - Standard | PENDING ASSIGNMENT | |||
| 05/06/2026 | Transportation Application Review Express | PENDING ASSIGNMENT | |||
| 05/08/2026 | ROW Engineering Review - Standard | REQUIRES RESUBMIT | DTM Review Comments - Required for Review Completion- 1) REQUIRED - Upload PIA and DEV Construction plan packets showing HAWK Crossing Build. 2) Review Traffic Control Plan Redline comments - Plan #2 Phase 2 - For Traffic Safety - Review to prevent Cross traffic through closure.. Barricade VP at 20' Spacing, Add in No Right Turn Signs at Driveways on Northside and to Side streets on South side. Plan #1 Phase 1 - Add Pedestrian Crossing Signs at side roads and driveway. Review for STOP sign placement as part of the ADA detour route |