Plan Number: TP-PRE-0723-00280
Parcel: 14102013C

Review Status: Approved

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - TP-PRE-0723-00280
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Entitlements REVIEW COMPLETED DATE: 8/16/2023
REVIEWED BY: Gabriel Sleighter, Planner
CASE NUMBER: TP-PRE-0723-00280 Tucson Water Well Site - Valencia
PROJECT ADDRESSES: 9355 E Valencia Road
PARCEL NUMBERS: 141-02-013C
EXISTING ZONING: SR
EXISTING USE: Vacant
PROPOSED ZONING:
PROPOSED USE: New Tucson Water well site

PROJECT DESCRIPTION & LOCATION:
The applicant has made a presubmittal request for a Zoning Examiner special exception procedure supporting the construction of a new Tucson Water well site at 9355 E Valencia Road. The development site is located within an approximately 26.8-acre parcel addressed 9355 E Valencia Road, approximately 1.2 miles west of the intersection of Valencia Road and Houghton Rd. The site, owned by City of Tucson, is currently vacant. The proposed land use is utilities distribution, which requires the zoning examiner special exception process and compliance with use-specific standards 4.9.11.A .1, .2, .5, .8, .9, .11, and .12.

APPLICANT NAME: CHARLES SULIK, SMYTH INDUSTRIES
E-MAIL: csulik@smythindustries.com

PLAN DIRECTION

ADOPTED PLAN (S): PLAN TUCSON, SOUTH PANTANO AREA PLAN

PLAN AMENDMENT REQUIRED BASED ON CONCEPT PRESENTED (SEE NOTES BELOW)

0 YES 1 NO 0 TO BE CONFIRMED LATER
NOTE: THE NORTHSIDE PLAN DOES NOT SUPPORT THE 3 STORIES ON THE NORTHERN PARCELS

PLAN SUPPORT BASED ON CONCEPT PRESENTED (SEE NOTES BELOW):

1 YES 0 NO 0 WILL DEPEND ON DESIGN







Applicable Plan Policies: Plan Tucson
Policy direction in Plan Tucson encourages the improvement of the appearance of above-ground utilities and structures and require development to support infill and redevelopment projects that reflect sensitivity to site and neighborhood conditions and adhere to relevant site and architectural design guidelines. Policies also call to prioritize, invest in, and maintain public infrastructure, including expanding the use of state-of-art, cost-effective technologies, and services for public infrastructure and facilities.

South Pantano Area Plan
The South Pantano Area Plan contains no land use direction specific to Utilities Distribution Land Use.

Surrounding Zoning and Land Uses: The subject parcel is zoned SR and is currently vacant. The parcel east of the project site is also zoned SR, and the current land use is a house of worship. Valencia Road borders the site to the south and is designated as an arterial gateway with a proposed right-of-way width of 150 feet per the Major Streets and Routes Overlay. Opposite the project site to the couth, the parcel is zoned C-2 with multifamily residential land use. The parcel to the west is also zoned SR, and the land is the southeast periphery of Davis Monthan Air Force Base.


Analysis:
The proposed well site and utilities distribution land use is in general compliance with Plan Tucson and the South Pantano Area Plan, provided use-specific standards are met. Applicant should proceed with notification procedure for a neighborhood meeting, staff is in support of this proposal.

A plan amendment is not required.


ADDITIONAL NOTES:
Fire New Construction REVIEW COMPLETED TP-PRE-0723-00280 • Pre-Application Conference Review v1 • 9355 E VALENCIA RD TUCSON, AZ 85747: Based on the information provided, TFD has no comments at this time.
Questions: patricia.shelton@tucsonaz.gov / 520.837.7082
Site Engineering REVIEW COMPLETED 1. Site Engineering has no comments or objections to the proposed zoning exception request

Scott Haseman
scott.haseman@tucsonaz.gov
Site Landscape REVIEW COMPLETED PROJECT: SPECIAL EXCEPTION – WELL SITE
ACTIVITY NO: TP-PRE-0723-00280
ADDRESS/PARCEL NO: 9355 E VALENCIA RD/141-02-013G
CURRENT ZONING:SR

EXISTING USE: VACANT LAND
PROPOSED USE: UTILITY DISTRIBUTION

TRANSMITTAL DATE: AUGUST 8, 2023
DUE DATE: AUGUST 16, 2023

COMMENTS:
1. There must be a NPPO. An NPPO is required per UDC 7.7.3-B. The NPPO is intended to encourage preservation in place of healthy native plants through sensitive site design that minimizes the disruption of areas within the site containing plants while allowing for salvage and transplantation of plants on the site that are likely to survive. A Native Plant Preservation Plan, Section 7.7.4, is required to be submitted or approved or a request for an exception from the Native Plant Preservation requirements approved in accordance with Sections 7.7.3.D.3 & .4 of the UDC and Admin. Manual Section 2-11.0.0 prior to Grading Plan approval. Maximize the number of preserve in place specimens to the fullest extent possible.
2. Ensure the required number of trees is in all vehicular parking areas (1 tree: 4 parking spaces) per UDC 7.6.4.B.1. Trees are to be distributed evenly throughout the parking area, UDC 7.6.4.1.B.1, UDC Technical Standards Manual 5-01-.3.2 and UDC 7.6.4.B.1.a.
3. There will need to be a street landscape border on Valencia Rd per UDC 7.6.4.C-2 and Table 7.6.4-1. See UDC 7.6.4.C for landscape border requirements.
4. . The walls shall be constructed of, or painted with, graffiti-resistant materials that blend into the natural open space of the parcel. The wall shall incorporate one or more of the following decorative materials: Tile; Stone ;Brick ;Adobe ,a textured material such as stucco or plaster; or metal.
5. Maximize rainwater harvesting across the entire site into the landscaped areas, this includes all landscape borders.
6. The use of flush curbs and parking blocks is strongly encouraged adjacent to all landscaped areas to help maximize rainwater harvesting across the site and meet the Commercial Rainwater Harvesting and First Flush demands.
7. A Commercial Rainwater Harvesting Plan is waived due to the nature of the site itself and the limited amount of new surfacing being added.

If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988
Site Zoning REVIEW COMPLETED Special Exception Pre-Submittal Transmittal

FROM: Nick Martell
PDSD Zoning Review

PROJECT: Rezoning Pre-submittal meeting TP-PRE-0723-00280
Address: 9355 E Valencia Rd
Parcel(s): 141-02-013G
Existing Zoning: SR
Existing Use: Utility Distribution


TRANSMITTAL DATE: March 15, 2022

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. The Utility Distribution-General use is subject to a Zoning Examiner Special Exception Procedure per 3.4.3 (UDC)
3. Proposed use and use-specific standards: 4.9.11.A. 1, .2, .5, .8, .9, .11, .12
4. Development standards:
a. 30 ft building height per TABLE 6.3-1.A
b. 50% Lot Coverage Maximum per TABLE 6.3-1.B
5. Perimeter yard setbacks: Adjacent to Residential Zones: 20’ per 6.3-1.A
6. Applicable street setbacks: E Valencia is a Major Street, and is subject to a 10’ setback per 6.4.5 UDC.
7. Parking requirements: See UDC Article 7.4.4 https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az_udc/0-0-0-5445
8. Bike parking requirements: See UDC Article 7.4.8 https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az_udc/0-0-0-5698
9. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.