Permit Number: TD-DEV-1224-00346
Parcel: 13216628B

Address:
1070 E AJO WY

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-1224-00346
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
01/23/2025 Commercial Plumbing APPROVED
01/28/2025 CDRC Post Review Express PENDING ASSIGNMENT
01/23/2025 External Reviewers - Arizona Department of Transportation (ADOT) REQUIRES RESUBMIT Good Afternoon,

ADOT has reviewed this DEV and has the following comments;

Has a traffic study been prepared for this DEV?
This DEV will add traffic to the transportation system due to being two commercial buildings on a parcel where there was previously one.
Consideration by the COT DTM should be exercised in determining if Off-Site improvements would be required.
Internal circulation appears to be restrictive as well.

Thank you for the opportunity to review.
01/28/2025 NPPO REQUIRES RESUBMIT See Site Landscape comments for NPPO Waiver requirement for the project.

Thank you.
Chad Keller, RLA
chad.keller@tucsonaz.gov
01/06/2025 ROW Engineering Review REQUIRES RESUBMIT TD-DEV-1224-00346 • 1070 E AJO WY

1. Per Sec 10-01.3.3 of the Technical Standards Manual, a pedestrian circulation path will have to be provided along the development's street frontage as specified in Sec. 10-01.4.0, this includes bringing the curb access ramps at the SE corner of Ajo Way and Park Ave and at the west side of the eastern driveway into compliance.

2. Revise keynote 34 to indicate that the concrete bus bay will be repaired per PAG SD 216, Type 3.

If you have any questions, please contact Richard Leigh at richard.leigh@tucsonaz.gov.
01/24/2025 Site Engineering REQUIRES RESUBMIT 1. There are several parking areas proposed with no pedestrian circulation nearby. Per TSM 7-01.4.1.D sidewalks must connect all areas of the development. Please add sidewalks, pedestrian crossings, and/or pedestrian refuge areas to provide safe access from all parking areas to the buildings.
2. On the utilities plan sheet please add "new utility service connections by separate permit" where applicable.
3. Please provide the slope for the proposed areas of grouted riprap slope stabilization. Please explain or provide more information as to why certain areas along this southern property line are proposed to have slope stabilization and others are not. Please explain why no slope stabilization is provided adjacent to the retention basin south of the proposed grouted riprap and waste enclosure. Infiltration in close proximity to a steep slope may cause erosion problems.

Mike Ortiz
michael.ortiz@tucsonaz.gov
01/28/2025 Site Landscape REQUIRES RESUBMIT CDRC TRANSMITTAL
PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: TWO NEW FOOD SERVICE BUILDINGS
ACTIVITY NO: TD-DEV-1224-00346
ADDRESS: 1070 E AJO WY
ZONING: I-1 LIGHT INDUSTRIAL ZONE
LAND USE: COMMERCIAL

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.

Please resubmit revised drawings along with a detailed response letter, which states how all of the Site Landscape/NPPO Section review comments have been addressed.

SITE LANDSCAPE/NPPO SECTION COMMENTS:

1. Even though the plans indicate that existing natives and other plants will be utilized within the design, we would still like to see a NPPO Waiver for our records with this project.

2. As a standard practice, a few spot elevations on the CRWHP at the bottom of basin and basin curb cut inlets and outlets that match the civil grading plan for coordination between the plans should be included. It is noted to see the civil grading plan for grading information, which is good. For redundant clarity adding a few spot elevations in key locations as a quick reference for the contractor and inspectors will be helpful.

3. The basin in the southeast corner has Ocotillo and Barrel Cacti at the bottom. Will the Barrel and Ocotillo survive if they sit in too much standing water during Monsoon? If you think that these plants shown in the depressed area will be okay, then can the other areas (2C, 1H, 1I and 1J) be depressed and coordinated between the CRWHP and the Civil Grading Plan? Or should the Barrels and Ocotillo be moved toward the top edge of the basin?

4. Make sure all trees are placed so that they don’t have a conflict with any utility lines. The street landscape border trees along Ajo may be a little close to some utility lines (middle Texas Ebony). If you feel that Texas Ebony stay small enough in stature and won’t affect the new water line, then I am okay with its proximity.

5. Can a leader callout be added to the planting plan to see detail G – Depressed Landscape Area for contractor reference.

6. Can the note be added to the tree planting detail about multi-trunk trees not needing to be staked if it is standing upright once the nursery stake is removed?

7. Can all reference to screened rock also indicate that the rock will be washed. The wording “washed screened rock” will help with any miscommunication between what is approved on the plans and what is implemented on site. There have been instances out on completed project sites where the quantity of fines in the rock mulch have been very high and not meeting the intent of how the rock mulch should function and appear aesthetically. This is a general recommendation. If this is something that you’re not comfortable specifying, it is okay to spec the screen rock as you have it currently.

8. Provide the development package case number, TD-DEV-1224-00346, adjacent to the title block on all sheets. 2-06.4.3

9. Prior to Site Landscape Development Package approval, please make sure Site Zoning and Site Engineering comments are addressed.

If you have any questions about these comments, I can be reached at chad.keller@tucsonaz.gov
or at 520.837.4923
01/21/2025 Site Zoning REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: SEC Park Av. and Ajo Wy.
Development Package (1st Review)
TD-DEV-1224-00346

TRANSMITTAL DATE: January 21, 2025

DUE DATE: January 23, 2025

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is December 30, 2025.

2-06.4.0 CONTENT REQUIREMENTS

1. COMMENT: 2-06.4.3 – Provide the development package case number, TD-DEV-1224-00346, adjacent to the title block on all sheets.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

2. COMMENT: 2-06.4.7.A.4 – Based on current aerial photos this site is currently vacant. The Existing use should be vacant and proposed use should be food service, General Note 3.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

3. COMMENT: 2-06.4.9.H.5.a – For the angled parking detail provide a C- Space Depth & E – Curb Length dimension, see UDC Figure 7.4.6-A.

4. COMMENT: 2-06.4.9.H.5.d – The short-term bicycle parking detail does not address the requirements of UDC Article 7.4.9.B.2.g.

5. COMMENT: 2-06.4.9.R – Clearly demonstrate that the requirements of TSM Section 701.3.3.A & 7-01.4.1.A are met out to Park Ave.

6. COMMENT: 2-06.4.9.R – Clearly demonstrate how the requirements of TSM Section 7-01.3.3.B are met between the two buildings.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf.
12/23/2024 CDRC Application Completeness Express REVIEW COMPLETED
01/02/2025 CDRC Review Coordinator Express REVIEW COMPLETED CDRC added TAA, Addressing, ADOT, and TEP-PAG, USPS, SWG to the workflow. Review request email sent to TAA, Addressing, ADOT, and TEP. FYI email sent to PAG, USPS, SWG.
01/08/2025 External Reviewers - Pima Association of Governments REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
01/23/2025 External Reviewers - Pima County Addressing REVIEW COMPLETED Good afternoon,



Pima County Addressing approves TD-DEV-1224-00346 - SEC Park & Ajo.
01/08/2025 External Reviewers - Southwest Gas REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
01/23/2025 External Reviewers - Tucson Airport Authority REVIEW COMPLETED January 22, 2025
Planning and Development Services
City of Tucson
201 North Stone Avenue
Tucson, AZ. 85701
RE: TD-DEV-1224-00346, Two new food service buildings, Received January 2, 2025
To whom this may concern,
Thank you for the opportunity to comment on TD-DEV-1224-00346, the development plan for two new food service buildings. This development is located in the N.E. quarter of the N.W. quarter of Section 31, Township 14S, Range 14E, of the Gila and Salt River Meridian. The development site occupies parcel numbers 132-16-628B, covers approximately 1.5 ± acres, and is zoned as Light Industrial Zone (I-1). The nearest major roadway intersection is East Ajo Way and South Park Avenue, approximately 50 feet to the northwest of the subject development.
This site does lie within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace.
The Tucson Airport Authority approves the 1st submittal of this project and is not requiring a resubmittal of this project.
Although this project does not propose a change in plan designation or zoning the Tucson Airport Authority highly recommends the applicant add the following notes into the general notes of the revised development plan. This project is located approximately 3 miles north of Tucson International Airport and is within FAA traffic pattern airspace, an area which would be subject to aircraft overflight and noise due to being in close proximity to Tucson International Airport.
The proposed notes would provide a means of assuring that future owners and tenants of the property are aware they are in proximity an airport and further assures the continued right of the City of Tucson, Tucson Airport Authority, and all persons lawfully utilizing the Tucson International Airport the right to utilize the airspace above or near the property. This would be accomplished through the property owner recording the Avigation Easement and providing the Airport Disclosure Statement to the new residents of all residential uses. The Tucson Airport Authority believes the proposed note helps to support the City of Tucson Airport Environs Overlay Zone and supports Plan Tucson – Regional and Global Positioning policy 4 (RG-4).
1."That prior to the City's approval of the proposed development, the property owner must record the Avigation Easement that discloses the existence and operational characteristics of the Tucson International Airport to future owners or tenants of the property and further conveys the right to the public to lawfully use the airspace above the property. The Avigation Easement shall be recorded in a manner with the Pima County recorder which shall document it as having title liability. The content of such documents shall be according to the form and instructions provided.”
The current property owner or person authorized to sign on behalf of the current property owner must complete, sign, and record the Avigation Easement. Please record the Avigation Easement with the Pima County Recorder’s Office. Then send a complete copy of the recorded easement document to Tucson Airport Authority by either email (send to srobidoux@flytucson.com) or to the mailing address provided below.
Scott Robidoux
Manager of Planning
Tucson Airport Authority
7250 South Tucson Blvd, Suite 300
Tucson, AZ 85756”
2.
Applicable to residential uses only
“The property owner/developer/applicant must provide the Airport Disclosure Statement form, at time of sale, to the new property owners with all new unit purchases. In the event the development of any residential uses does not involve the sale of new units but is instead offering rental residential units to the public, the new tenant of the rental unit must be provided a copy of the Airport Disclosure Statement form. The intent of the Airport Disclosure Statement form is to educate and notify the new residents that they are living near an airport. The content of such documents shall be according to the form and instructions provided.”
The property owner (for itself or its tenants) shall forward a signed copy of the Airport Disclosure Statement form to the Tucson Airport Authority within ten (10) days of signature, using the Scott Robidoux mailing address provided above.
Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811.
Respectfully,
Scott Robidoux, C.M.
Manager of Planning
cc file
01/24/2025 External Reviewers - Tucson Electric Power (TEP) REVIEW COMPLETED January 24, 2025
WO#T139019
CITY OF TUCSON
PLANNING AND DEVELOPMENT SERVICES
Attn: CDRC ADMIN TEAM
Dear CDRC ADMIN TEAM
Subject: SEC PARK AV AND AJO WAY
TD-DEV-1224-00346
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 1/10/2025. There are existing facilities within the development which are
depicted upon the plan; however there do not appear to be any apparent conflicts at this
time.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
MARTIN SALAZAR
(520) 305-6713
msalazar@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
01/08/2025 External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
01/15/2025 Fire New Construction REVIEW COMPLETED
12/31/2024 OK to Submit - Engineering Fast REVIEW COMPLETED
12/31/2024 OK to Submit - Zoning Fast REVIEW COMPLETED