| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/10/2026 | NPPO | APPROVED | |||
| 04/10/2026 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 03/25/2026 | ROW Engineering Review | REQUIRES RESUBMIT | Show Alley section, cross slope should follow Technical Standards manual. Show 18' Radius for additional alley dedication by seperate instrument on SW corner of parcel 12901013A. |
||
| 03/24/2026 | Site Engineering | REQUIRES RESUBMIT | Permit Activity Number: TD-DEV-1124-00316 (1st Review) Project: New parking lot Location: 150 S TUCSON BL Review Date: 3/23/2026 Reviewers: Marco Contreras – Engineering Associate - Site Engineering & Joe Macaulay – Civil Engineer Related Cases: *This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-6 and Technical Standards Manual (TSM) Section for waste management, Pedestrian Access, Hydrology -Retention/Detention Requirements, and all site standard code. * City of Tucson Code: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes Floodplain Code: https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az/0-0-0-19333 Drainage Manual Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/cot-drainage-manual-searchable.pdf Design standards for Stormwater Detention and Retention Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf Site Engineering Review Comments: 1. Demonstrate compliance with minimum freeboard requirements for all water harvesting basins. DSSDR 5.3.1.3 2. Demonstrate setback compliance regarding the trash enclosure and water harvesting basins. DSSDR 5.3.1.11 3. Provide a simple summary table in the conclusion portion of the report to compare the Pre-Development Vs. Post-Development peak discharges for the 2-, 10-, & 100-yr events to clearly show that the development falls within compliance with balanced basin detention requirements 4. Provide all City of Tucson Hydrologic Data sheets used for computing the 2-, 10-, & 100-year peak discharges. Pima County Data sheets will not solely accepted. 5. Provide An inspection and maintenance protocol including frequency of inspection, a checklist of items to be inspected and recommended maintenance when an inspection identifies a maintenance requirement shall be prepared by an Arizona registrant should be included at the end of the provided drainage report. DSSDR 4.1.1 6. Show the 2ft minimum grading setback from the property line on the grading plan TSM 2-01.9.0. Demonstrate the limits of grading along the south, west, & east property lines of the site. A reduced setback will require geotechnical justification that no adverse impacts will be caused by the proximity of grading and drainage infrastructure within the minimum 2-foot setback. 7. Show compliance with UDC 7.4.6.F.2.b in regard to the existing power poles along the northing island/long-term bicycle parking. There is po 8. Referring the east parking spaces, Wheel stops will be required at all parking spaces adjacent to the sidewalks/pathways so as not to reduce the sidewalk path to less than 4 feet. UDC 7.4.6 Sidewalks that are 6 and a half feet or wider will not require adjacent parking spaces to have wheel stops. This should be addressed for all spaces where the pathway can be reduced below said 4-ft requirement. 9. A Bollard or some type of barrier will be required for the 9-foot curb opening to prevent a vehicle encroaching into the water harvesting area. If you have any questions or concerns, please contact Marco Contreras at Marco.contreras@tucsonaz.gov or Joe Macaulay at Joe.Macaulay@tucsonaz.gov |
||
| 04/10/2026 | Site Landscape | REQUIRES RESUBMIT | PLANNING AND DEVELOPMENT SERVICES DEPARTMENT REVIEWER: CHAD KELLER, RLA SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION PROJECT: NEW PARKING LOT ACTIVITY NO: TD-DEV-1124-00316 RELATED ACTIVITY NO: TD-DEV-1124-00315 ADDRESS: 150 S TUCSON BL ZONING: C-1 COMMERCIAL ZONE; UOD 3 SUNSHINE MILE (MID CENTURY SUBDISTRICT) 2026.04.10 THE PROPOSED PLANS HAVE BEEN REVIEWED FOR COMPLIANCE WITH APPLICABLE DEVELOPMENT STANDARDS FOR SITE LANDSCAPE, NATIVE PLANTS, AND RAINWATER HARVESTING, PER-THE-CITY OF TUCSON UNIFIED DEVELOPMENT CODE (UDC), TECHNICAL STANDARDS MANUAL (TSM), AND ADMINISTRATIVE MANUAL (AM). RESUBMIT REVISED DRAWINGS ALONG WITH A DETAILED RESPONSE LETTER, STATING HOW ALL SITE LANDSCAPE AND NPPO SECTION REVIEW COMMENTS HAVE BEEN ADDRESSED. SITE LANDSCAPE/NPPO SECTION COMMENTS: 1. The related development packages (TD-DEV-1124-00315 and TD-DEV-1124-00316) for this project are considered one site review. All comments for both development packages must be addressed prior to approval. 2. Include spot elevations at curb cut inlets, bottom of basin and curb cut outlets for quick reference during site inspections. Include this information on both DP’s where applicable. Thank you. Chad Keller, PLA Landscape Architect chad.keller@tucsonaz.gov 520.837.4923 |
||
| 03/27/2026 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Loran Shamis PDSD Zoning Review Section PROJECT: Stravenue Social Parking lot Development Package (1st review) TD-DEV-1124-00316 (150 S TUCSON BL TUCSON, AZ 85719) TRANSMITTAL DATE: March 27, 2026 DUE DATE: April 7, 2026 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is March 13, 2027. SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS) 1. COMMENT: Per UDC 7.4.6.H.1, barriers, such as post barricades or wheel stop curbing, are required in a vehicular use area to prevent vehicles from overhanging adjacent sidewalk areas. Please provide wheel stops for the parking spaces along the eastern property line to ensure vehicles do not overhang into the minimum required sidewalk width of 4 feet (TSM 7-01.4.3.A) 2. COMMENT: Per UDC 7.4.6.B.1.b, off-site parking is permitted so long as the off-site parking location has parking in excess of the minimum required parking for its use. Please provide the parking calculation included on TD-DEV-1124-00315, for the minimum required parking including the parking calculation provided here stating this parking use required 0 parking spaces. 3. COMMENT: 2-06.4.9.H.5.b - Per UDC 7.4.6.B.1.d, and SMD III.H.1.a.2.c, A recorded Shared Parking Agreement for the parking to be located off-site must be provided prior to issuance of the associated building per SMD III.H.3.b. A condition shall be placed on building permits TC-COM-0325-00503 and TC-COM-0325-00504 to provide this information prior to final Certificate of Occupancy. ***For additional information on the any standard presented in this memo, please refer to the City of Tucson “Unified Development Code” – Administrative Manual Section 2-06 or Technical Standards noted in the comments. https://www.tucsonaz.gov/pdsd/all-codes-plans-determinations If you have any questions about this transmittal, Contact Loran Shamis by email Loran.Shamis@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package and comment response letter. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home. Instructions for resubmittal - https://www.tucsonaz.gov/files/pdsd/website/Resubmittals.pdf. |
||
| 03/23/2026 | CDRC Review Coordinator Express | REVIEW COMPLETED | CDRC added ADOT, TEP, PAG, USPS, and SWG to the workflow. Review request email sent to ADOT, and TEP. FYI email sent to PAG, USPS, SWG. | ||
| 04/02/2026 | Commercial Plumbing | REVIEW COMPLETED | |||
| 03/26/2026 | Design Review | REVIEW COMPLETED | A recorded Shared Parking and Cross Access Easment Agreement to allow access from/to properties under TD-DEV-1124-00315 for parking and refuse collection must be approved by Zoning under TC-COM-0325-00503 (West building) and TC-COM-0325-00504 (East Building). If you have any questions, please let me know: maria.gayosso@tucsonaz.gov. Thank you. | ||
| 04/06/2026 | External Reviewers - Arizona Department of Transportation (ADOT) Standard | REVIEW COMPLETED | ADOT has no comments. Thanks, Rick Freije |
||
| 03/23/2026 | External Reviewers - Pima Association of Governments Standard | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | ||
| 04/06/2026 | External Reviewers - Southwest Gas Standard | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | ||
| 04/09/2026 | External Reviewers - Tucson Electric Power (TEP) Standard | REVIEW COMPLETED | April 9, 2026 WO#T180016 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: STRAVENUE SOCIAL - SOUTH TD-DEV-1124-00316 Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted 3/23/2026. There are existing facilities within the development which are not depicted upon the plan. Possible conflicts with TEP overhead pole line. Contact TEP Design if relocation is required. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918-8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Should you have any easement questions, please contact our Land Resources Department, LandReviews@tep.com. Should you have any technical questions, please contact the area designer, Martin Salazar (520) 305-6713 msalazar@tep.com Sincerely, Design Admins Design Admins Tucson Electric Power |
||
| 03/23/2026 | External Reviewers - United States Postal Service (USPS) Standard | REVIEW COMPLETED | CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required. | ||
| 04/07/2026 | Fire New Construction | REVIEW COMPLETED | |||
| 03/27/2026 | Historic | REVIEW COMPLETED | No historic resources impacted. | ||
| 03/18/2026 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 03/20/2026 | OK to Submit - Zoning Fast | REVIEW COMPLETED |