Permit: TD-DEV-1124-00316
Permit Details
Apply Date:
11/22/2024
Applicant:
Anthony Chamberlain
Description:
Rev 1 - started 09/29/2026 - updates to utilities, bike locker New parking lot
Permit Reviews
Permit Number - TD-DEV-1124-00316
Permit Status: Issued
Permit Description: Rev 1 - started 09/29/2026 - updates to utilities, bike locker
New parking lot
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/29/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 10/23/2026 | APPROVED |
| 04/21/2026 | DEVELOPMENT PACKAGE NEW v.3 | 05/08/2026 | APPROVED |
| 03/16/2026 | DEVELOPMENT PACKAGE NEW v.2 | 04/10/2026 | REQUIRES RESUBMIT |
| 11/29/2024 | DEVELOPMENT PACKAGE NEW v.1 | 12/09/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-1124-00316
Permit Status: Issued
Permit Description: Rev 1 - started 09/29/2026 - updates to utilities, bike locker
New parking lot
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 05/01/2026 | CRWH PLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
| 06/08/2026 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-1124-00316
Permite Description: Rev 1 - started 09/29/2026 - updates to utilities, bike locker
New parking lot
Total Outstanding Inspections - 1
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-1124-00316
Permit Description: Rev 1 - started 09/29/2026 - updates to utilities, bike locker
New parking lot
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2026 | PDSD Engineering Division Pre-Construction SITE | Passed |