Permit Number: TD-DEV-1024-00296
Parcel: 120090510

Address:
4407 S 6TH AV

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-1024-00296
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/26/2024 Commercial Plumbing APPROVED
12/04/2024 NPPO NOT REQUIRED
12/04/2024 Site Landscape NOT REQUIRED
12/04/2024 CDRC Post Review Express PENDING ASSIGNMENT
11/25/2024 External Reviewers - Tucson Electric Power (TEP) REQUIRES RESUBMIT November 25, 2024
WO#T133241
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Solar Canopy Plan 4407 South 6th Avenue
TD-DEV-1024-00296
Tucson Electric Power Company (TEP) has reviewed and cannot approve the
development plan submitted 11/12/2024. There are existing facilities within this
development which are not depicted upon the plan; specifically, an Overhead Service
Wire not shown on the plans will be in conflict.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
Fred Quintero
(520) 235-6329
fquintero@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
12/02/2024 Site Engineering REQUIRES RESUBMIT TD-DEV-1024-00296
4407 S 6TH AV TUCSON, AZ 85714

Site engineering comments are as follows:
1. The name of the street to the north of the site is misspelled as “Aviator” on the cover sheet. Please revise to “Aviation.”
2. Per Administrative Manual 2-06.3:
a. A three-inch by five-inch space shall be reserved in the lower right quadrant of each sheet for an approval stamp. 3.5
b. Provide a blank three-inch by five-inch block in the lower right corner of the plan adjacent to the title block on the first sheet of the development package for use by Pima County Addressing. 3.6
c. A small, project-location map shall be provided in the upper right corner of the cover sheet. 3.7
d. A legend that shows and describes all symbols used on the drawing is to be provided, preferably on the first sheet. 3.10
3. Per Administrative Manual 2-06.4:
a. The name, mailing and email addresses, and phone number of the primary property owner of the site, the developer of the project, registrant(s), and other person(s), firm(s), or organization(s) that prepared the development plan documents shall be provided on the right half of the cover sheet. The applicable registration or license number shall be provided if prepared by or with the assistance of a registered professional, such as a surveyor, architect, landscape architect, or engineer. All sealing shall be consistent with Arizona Board of Technical Registration guidelines.
b. The administrative street address and relevant case numbers (development package document, subdivision, rezoning, board of adjustment, DDO, MDR, DSMR, overlay, etc.) shall be provided adjacent to the title block on each sheet. 4.3
c. The project-location map to be located on the first sheet of the development package in the upper right corner, shall cover approximately one square mile, be drawn at a minimum scale of three inch equals one mile, and provide the following information. 4.4
• Show the subject property approximately centered within the one square mile area.
• Identify major streets and regional watercourses within the square mile area and all streets that abut the subject property.
• Section, township, and range; section corners; north arrow; and the scale will be labeled.
4. See Zoning comments 8 thru 10 regarding site information requirements.
Ryan Insalaco
ryan.insalaco@tucsonaz.gov
11/25/2024 Site Zoning REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: Ramiro Olivarez
PDSD: Zoning Review

PROJECT: Solar Shade Structure - 4407 S 6TH AV
Development Package (1st Review)
TD-DEV-1024-00296

TRANSMITTAL DATE: November 25, 2024

DUE DATE: December 02, 2024

CHECKLIST FOR MINOR DEVELOPMENT CHANGES TO EXISTING
COMMERCIAL/INDUSTRIAL SITES

Purpose
This standard has been prepared for the purpose of informing applicants of the
submittal and review requirements for minor changes to existing commercial sites to
assure proper and adequate information is presented in a consistent manner,
thereby providing the basis for an efficient and timely review. The minor revisions to
existing commercial sites are prepared in support of applications for building permits
and related reviews.

The information that is requested establishes the basis upon which the project will
be approved and could affect what is required of the property in the future, should
there be a proposal for expansion or for a different use of the property. This standard
does not waive any applicable city regulations or codes.

Applicability
This standard shall be used for minor changes to existing commercial sites such as
but not limited to; expansions less than 25% in square footage of land area, floor
area, lot coverage, or vehicular use area, modification to accessible vehicle parking,
parking area restripe, etc. Applicability to be determined by Zoning and/or
Engineering review staff via email or at PDSD review counter

APPLICATION SUBMITTAL REQUIREMENTS
Development Package applications are available from PDSD. Completed
applications and accompanying materials shall be submitted to PDSD. Incomplete or
inaccurate applications will not be accepted. The types of documents and the
specific number of copies required of each of the documents are on the PDSD
website or may be obtained from PDSD. Resubmittals of development packages
require a comment response letter that details how all previous comments have
been addressed. Provide the same number of copies of the comment response
letter as plans provided.
The following documents and information shall be submitted upon application:
1. A completed application signed by the property owner or authorized designed.
2. A development package must be prepared to the format and content
requirements described herein.
3. Fees in accordance with Section 4-01.0.0, Development Review Fee Schedule or
as determined on an hourly rate.

FORMAT REQUIREMENTS

6. A small, project-location map shall be provided in the upper right corner of the
cover sheet. This map shall cover approximately one square mile, be drawn at a
minimum scale of three inch equals one mile, and provide the following
information;

COMMENT: Locate the project-location map in the upper right corner as noted by the Standard above.

a. Show the subject property approximately centered within the one square
mile area. Identify major streets within the square mile area and all streets
that abut the subject property. Section, township, and range, north arrow,
and the scale will be labeled.

COMMENT: Identity all major streets including 12th avenue on the westside section line and SPRR on the east side section line. Label the section, township, and range as follows (Section 36, T 14 S, R 13 E) under the project location map and include G & SRM Pima County, Arizona. Label the scale of the project location map under the north arrow.

7. The north arrow, and scale as applicable to each sheet should be placed
together in the upper right corner of each sheet.
COMMENT: On the second sheet provide the north arrow and scale as noted in the Standard above.

CONTENT REQUIREMENTS
1. The name, mailing and email addresses, and phone number of the primary
property owner of the site, the developer of the project, registrant(s), and other
person(s), firm(s), or organization(s) that prepared the development package
documents shall be provided on the right half of the cover sheet. The applicable
registration or license number shall be provided if prepared by or with the
assistance of a registered professional, such as a surveyor, architect, landscape
architect, or engineer. All sealing shall be consistent with Arizona Board of
Technical Registration guidelines.

COMMENT: List all the applicable personnel information as noted in the Standard above.

2. The title block shall include the following information and be provided on each
sheet: The proposed name of the project, or if there is no name, the proposed
tenant’s name. A brief legal description is to be provided. The page number and
the total number of pages in the package (i.e., sheet xx of xx). The administrative
street address and relevant case numbers (development package document,
subdivision, rezoning, board of adjustment, DDO, MDR, DSMR, overlay, etc.)
shall be provided adjacent to the title block on each sheet.

COMMENT 1: Relocate the surveyor information out of the title block. List in the title block the legal description.

COMMENT 2: A Design Development Option (DDO) may be required for the north and east building setbacks as it relates to the proposed solar canopy.

GENERAL NOTES
The following general notes are required. Additional notes specific to each plan are
required where applicable.
3. Identify the existing and proposed use of the property as classified per the UDC.
List all UDC sections applicable to the proposed uses.

COMMENT 1: List as a general note the existing use per the most current approved Certificate of Occupancy (CofO), Food Service (T09OT00500). If the use is different from the last approved CofO then provide the documentation for the current or new use of this property as noted by the Standard above.

COMMENT 2: List the proposed use for the solar canopy.

5. Percentage of gross floor area, land area, or vehicular use area expansion. If the
building(s) or lot area have been previously expanded, those calculations shall
be included.
COMMENT: The solar canopy is considered a new structure. As a general note list the square footage and use of the solar canopy such as outside seating, parking, etcetera as noted by the Standard above.

EXISTING SITE CONDITIONS:
2. All existing easements shall be drawn on the plan. The recordation information,
location, width, and purpose of all easements on site will be stated.

COMMENT: Add all recordation information for all utility’s drawn and labeled on the plan.
(Clarify if the existing building is built over the southern property line. And if so provide any documentation. Dimension the area of the building that encroaches into south adjacent property.)

3. The following information regarding existing private or public right-of-way
adjacent to or within the site shall be provided: the name, right-of-way width,
recordation data, type and dimensioned width of paving, curbs, curb cuts, and
sidewalks.

COMMENT: Label the R/W as depicted on the plan as “1/2 R/W” for 6th Ave. and Aviation Dr. Draw, label, and dimension the width of paving, curbs, curb cuts, and sidewalks as noted by the Standard.

INFORMATION OF PROPOSED DEVELOPMENT:
The following information on the proposed project shall be shown on the drawing or
added as notes.

1. All existing zoning classifications on and adjacent to the project (including across
any adjacent right-of-way) shall be indicated on the drawing with zoning
boundaries clearly defined.

COMMENT: Label all zoning classifications including all properties adjacent and across both streets, 6th St and Aviation Ave as noted by the Standard above.

2. Show all motor vehicle off-street parking spaces provided, fully dimensioned. As
a note, provide calculations on the number of spaces required (include the ratio
used) and the number provided, including the number of spaces required and
provided for the physically disabled. The drawing should indicate parking space
locations for the physically disabled. A typical parking space detail shall be
provided for both standard parking spaces and those for the physically disabled.
For information on parking requirements for the physically disabled, refer to
adopted building and accessibility codes of the City of Tucson. Design criteria for
parking spaces and access are located in Section 7.4.6, Motor Vehicle Use Area
Design Criteria, of the UDC.

COMMENT: Draw, label, and dimension all motor vehicle off-street parking spaces as noted by the Standard above.

3. Show bicycle parking facilities fully dimensioned. For specifics, refer to Section
7.4.9, Bicycle Parking Design Criteria, of the UDC. Provide, as a note,
calculations for short and long term bicycle spaces required and provided.

COMMENT: Draw, label, and dimension the bicycle parking facilities as noted by the Standard above.

5. All proposed easements (utility, sewer, drainage, access, etc.) are to be
dimensioned and labeled as to their purposes and whether they will be public or
private. The easements may have to be recorded and the recordation information
added to the development package prior to approval.

COMMENT: If applicable draw, label, and dimension all proposed easements as noted by the Standard above.

6. All applicable building setback lines, such as erosion hazard, floodplain
detention/retention basins, and zoning, including sight visibility triangles, will be
shown.

COMMENT 1: Draw, label, and dimension all building setback lines to the existing building. Label and dimension the existing setback from the property line along Aviation to the existing building and existing and future property line to the existing building along 6th Avenue frontage.

COMMENT 2: It has been noted the proposed solar canopy structure on the northern setback is 19.2’ and does not comply with the 20’ street setback when abutting a local street (Aviation). Also, the documentation for the solar canopy structure was not provided such as the height or elevations. Therefore, the east setback from the solar canopy to the property is based ½ times height of the top of the wall. The setback cannot be verified at this time until the solar canopy documentation is provided.

7. Provide the square footage and the height of each commercial, industrial, or
business structure and the specific use proposed within the footprint of the
building(s).

COMMENT: Provide the square footage and the height of all structures as noted by the Standard above.

8. Show on-site pedestrian circulation and refuge utilizing location and the design
criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards
Manual.

COMMENT: Show on-site pedestrian circulation and refuge utilizing location and the design
criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards
Manual as noted by the Standard above.

9. Show existing or proposed pedestrian circulation along abutting rights-of-way.
Such sidewalks must comply with accessibility requirements for the physically
disabled and the design criteria in Section 10-01.0.0, Street Technical Standards,
of the Technical Standards Manual.

COMMENT: Show existing or proposed pedestrian circulation along abutting rights-of-way.
Such sidewalks must comply with accessibility requirements for the physically
disabled and the design criteria in Section 10-01.0.0, Street Technical Standards,
of the Technical Standards Manual as noted by the Standard above.


10. Show refuse collection areas, including locations of dumpsters, screening
location and materials, and vehicle maneuverability, fully dimensioned, and
access route. If dumpster service is not proposed, indicate type of service. For
specific information on refuse collection, refer to Section 8-01.0.0, Solid Waste
and Recycle Disposal, Collection, and Storage, of the Technical Standards
Manual. Refuse collection on all projects shall be designed based on that
section, even if collection is to be contracted to a private firm.

COMMENT: Provide the information on the plan as noted by the Standard above.

11. Indicate the locations and types of proposed signs (wall, free-standing, pedestal)
to assure there are no conflicts with other requirements and that minimal
locational requirements can be met. Indicate if there are any existing billboards
on site. Compliance to the Sign Code, Chapter 3 of the Tucson Code, is required.

COMMENT: If applicable, provide the information on the plan as noted by the Standard above.

12. Show compliance with landscaping and screening requirements by locations,
material descriptions, and dimensions. Specific plant or hardscape material shall
be detailed on a landscape plan. A detailed landscape plan is required. In
accordance with Section 2-11.0.0, Landscape Plan Requirements.

COMMENT: Provide the information on the plan as noted by the Standard above.



RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A corrected development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf

If you have any questions about this transmittal, please contact Ramiro Olivarez at Ramiro.Olivarez@tucsonaz.gov
10/31/2024 CDRC Application Completeness Express REVIEW COMPLETED
11/12/2024 CDRC Review Coordinator Express REVIEW COMPLETED CDRC added TEP to the workflow. Review request email sent to TEP.
11/17/2024 Fire New Construction REVIEW COMPLETED
11/08/2024 OK to Submit - Engineering Fast REVIEW COMPLETED
11/06/2024 OK to Submit - Zoning Fast REVIEW COMPLETED
11/15/2024 ROW Engineering Review REVIEW COMPLETED DTM has no comments.
12/03/2024 ROW Review REVIEW COMPLETED