Permit Number: TD-DEV-1023-00425
Parcel: 12418120C

Review Status: Approved

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-1023-00425
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
11/15/2023 Commercial Plumbing APPROVED
11/21/2023 External Reviewers - Tucson Airport Authority APPROVED November 20, 2023
Planning and Development Services
City of Tucson
201 North Stone Avenue
Tucson, AZ. 85701
RE: TD-DEV-1023-00425, Perception Counselling PV: Adding a new steel parking canopy structure in an existing parking area to support a total of 69 modules in a grid-tied PV system / 1213 E Warehouse Ave, Tucson, AZ 85719, Received October 26, 2023
To whom this may concern, Thank you for the opportunity to comment on TD-DEV-1023-00425, the development plan for constructing new solar array canopies in an parking lot at 1213 East Warehouse Avenue. This development is located in the N.W. quarter of the S.E. quarter of Section 18, Township 14S, Range 14E, of the Gila and Salt River Meridian. The development site occupies parcel number
124-18-120C, covers approximately 0.68 ± acres, and is zoned as Light Industrial Zone (I-1).
The nearest major roadway intersection is South Park Avenue and East 18th Street,
approximately 1,350 feet to the northwest of the subject development.
This site does lie within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace.
The Tucson Airport Authority approves the proposed project and is not requiring a resubmittal.
Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811.
Respectfully,
Scott Robidoux, C.M.
Manager of Planning
11/16/2023 ROW Engineering Review APPROVED No Comments

David Stiffey

David.Stiffey@tucsonaz.gov
11/21/2023 Site Engineering APPROVED
11/17/2023 Site Landscape APPROVED
11/03/2023 Site Zoning APPROVED
11/17/2023 NPPO NOT REQUIRED
10/16/2023 CDRC Application Completeness Express REVIEW COMPLETED
11/24/2023 CDRC Post Review Express REVIEW COMPLETED
10/26/2023 CDRC Review Coordinator Express REVIEW COMPLETED Review request email sent per ADOT and TAA, and FYI email sent per PAG, USPS, SWG & TEP.
11/01/2023 External Reviewers - Arizona Department of Transportation (ADOT) REVIEW COMPLETED Good Morning, ADOT has no comments on this DEV. Thank you for the opportunity to review.
10/26/2023 External Reviewers - Pima Association of Governments REVIEW COMPLETED FYI email sent per PAG, USPS, SWG & TEP.
10/26/2023 External Reviewers - Southwest Gas REVIEW COMPLETED FYI email sent per PAG, USPS, SWG & TEP.
10/26/2023 External Reviewers - Tucson Electric Power (TEP) REVIEW COMPLETED FYI email sent per PAG, USPS, SWG & TEP.
10/26/2023 External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED FYI email sent per PAG, USPS, SWG & TEP.
11/07/2023 Fire New Construction REVIEW COMPLETED
10/20/2023 OK to Submit - Engineering Fast REVIEW COMPLETED
10/17/2023 OK to Submit - Landscape Fast REVIEW COMPLETED