Permit Number: TD-DEV-1023-00417
Parcel: 115043060

Address:
1131 N 6TH AV

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.2

Permit Number - TD-DEV-1023-00417
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/17/2023 External Reviewers - Tucson Electric Power (TEP) APPROVED November 17, 2023
WO#T96422
City of Tucson
Planning And Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Montessori Schoolhouse
TD-DEV-1023-00417
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 11/8/2023. There are existing facilities within the development which are depicted upon the plan; there do not appear to be any apparent conflicts at this time however, TEP has an overhead line running North to South along the alley. The plans state that this electrical service will be removed or replaced.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans.
If easements are required, they will be secured by separate instrument. Your final
plans should be sent to:
Gabriela Bielecka
Tucson Electric Power Company
New Business Residential Project Manager
P. O. Box 711 (OH 204)
Tucson, AZ 85703
(520) 651-3833
Should you have any technical questions, please contact the area designer, Fred
Quintero at (520) 235-6329.
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
11/21/2023 NPPO APPROVED
11/16/2023 ROW Engineering Review APPROVED No Comments

David Stiffey

David.Stiffey@tucsonaz.gov
11/27/2023 Site Engineering APPROVED
11/21/2023 Site Landscape APPROVED
12/04/2023 CDRC Post Review Express PENDING ASSIGNMENT
11/20/2023 Commercial Plumbing REQUIRES RESUBMIT Provide the rim elevation of the next upstream sanitary manhole. Determine the need for a backwater valve for the proposed building per Section 714.1, IPC 2018, as amended by the City of Tucson.
11/13/2023 Site Zoning REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Montessori Middle School – 1131 N. 6th. Ave
Development Package (1st Review)
TD-DEV-1023-00417

TRANSMITTAL DATE: November 13, 2023

DUE DATE: November 28, 2023

COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

The Zoning review is for review of the proposed accessible vehicle parking.

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is October 31, 2024.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

1. COMMENT: 2-06.4.9.H.5.a – Per the 2018 IBC Section 1106.5 the proposed HC parking space is required to be a van accessible parking space meeting the requirements of ICC A117.1, Section 502.2.

2. COMMENT: 2-06.4.9.H.5.a – Detail 1 sheet 3 the mounting height shown for the accessible sign is not correct and should be 60” is not located within a pedestrian circulation and 74” if located within a pedestrian circulation as measured from the bottom of the lowest sign.

If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package & detailed response letter.
10/27/2023 CDRC Application Completeness Express REVIEW COMPLETED
11/04/2023 CDRC Review Coordinator Express REVIEW COMPLETED Review request email sent per ADOT and TEP, FYI email sent to PAG, USPS, SWG.
12/04/2023 External Reviewers - Arizona Department of Transportation (ADOT) REVIEW COMPLETED Good Afternoon,
I apologize for the delay in response, ADOT has no comments on this DEV.
Thank you for the opportunity to review.
11/04/2023 External Reviewers - Pima Association of Governments REVIEW COMPLETED CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time.
11/04/2023 External Reviewers - Southwest Gas REVIEW COMPLETED CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time.
11/04/2023 External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time.
11/20/2023 Fire New Construction REVIEW COMPLETED
11/01/2023 OK to Submit - Landscape Fast REVIEW COMPLETED