Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: TD-DEV-0924-00272
Parcel: 133231470

Review Status: Approved

Review Details: DEVELOPMENT PACKAGE NEW REVISION v.2

Permit Number - TD-DEV-0924-00272
Review Name: DEVELOPMENT PACKAGE NEW REVISION v.2
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
09/18/2026 Site Engineering Standard APPROVED Permit Activity Number: TD-DEV-0924-00272
Project: Revision 2
Location: 7333 E ROSEWOOD ST
Review Date: 9/18/2026
Reviewer: Joe Macaulay – Civil Engineer – Site Development
Reviewer Contact Information: joe.macaulay@tucsonaz.gov



Site Engineering Review Comments:

The review has been completed by Site Engineering and approved under the following conditions:
1. Upon completion of site construction, an As-Built plan set documenting all revisions to the project that were constructed in the field will need to be submitted before final project close-out.
a. The As-Built plans shall reflect the final constructed conditions and include all field changes or revisions from the approved construction documents with the revisions clearly identified throughout the applicable plan sheets as noted in comments #2 and #3 below.
2. Provide clouded linework around all information effected by the submitted revision on each applicable plan sheet. Each revision cloud shall be identified with a corresponding triangular revision number.
3. Provide a revision description table on each plan sheet, including the cover sheet.
a. The table shall identify the applicable triangular revision number and provide a brief description that accurately corresponds to the submitted revision number shown on that sheet to allow the information to be readily correlated throughout the plan set.
09/18/2026 Site Zoning Standard APPROVED
08/27/2026 CDRC Application Completeness Express REVIEW COMPLETED
09/22/2026 CDRC Post Review Express REVIEW COMPLETED
09/02/2026 CDRC Review Coordinator Express REVIEW COMPLETED
09/21/2026 Commercial Plumbing Standard REVIEW COMPLETED
09/18/2026 Fire New Construction Standard REVIEW COMPLETED
09/01/2026 OK to Submit - Engineering Fast REVIEW COMPLETED
08/31/2026 OK to Submit - Zoning Fast REVIEW COMPLETED