Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.3
Permit Number - TD-DEV-0623-00280
Review Name: DEVELOPMENT PACKAGE NEW v.3
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/28/2023 | External Reviewers - Tucson Airport Authority | APPROVED | The Tucson Airport Authority approves the 2nd submittal of this project and is not requiring a resubmit of this project. | ||
09/01/2023 | Site Landscape | APPROVED | |||
10/04/2023 | CDRC Post Review | PENDING ASSIGNMENT | |||
10/04/2023 | Site Engineering | REQUIRES RESUBMIT | 1. Include the approval documentation from Environmental Services for the proposed trash collection at this site. 2. Show how phase one will work independent from the other phasing including the full site compliancy triggered from the 25% expansion of the site. 3. If this is a Master Development Plan clarify that it is not to be used for construction on the plans. 4. Clarify what drainage infrastructure is going to be completed during which phase to ensure each phase works independent of future phase work. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
||
09/29/2023 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Wyatt Berger Lead Planner PROJECT: Goodwill Tucson Development Package (2nd Review) TD-DEV-0623-00280 TRANSMITTAL DATE: September 29, 2023 DUE DATE: September 29, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC), Administrative Manual (AM) Section 2-06, and the Technical Standards Manual (TSM). Per UDC Section 3.3.3.G.5.c, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year expiration date is September 29, 2024. 1. COMMENT: 2-06.4.7.A.4 – This comment was not entirely addressed. List all use-specific standards applicable to each proposed use within the development. 2. COMMENT: 2-06.4.9.E – This comment was not addressed. As the site is comprised of multiple parcels, provide either an approved lot consolidation request processed with the Pima County Assessor’s Office or a recorded Covenant Regarding Development and Use of Real Property: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/submission-documents/covenant-regarding-development-and-use-of-real-property-udc-with-release.pdf. 3. COMMENT: 2-06.4.9.G – This comment was not entirely addressed. As the project is anticipated to be phased, provide calculations, setbacks, etc., to indicate that each phase complies with all requirements as a separate entity. Ensure that motor vehicle bicycle parking requirements are also met for each phase as if the entire development were not to be fully built. 4. COMMENT: 2-06.4.9.H.5.a – This comment was not entirely addressed. Provide a proposed number of EV parking spaces. Additionally, one of these spaces is required to be accessible electric vehicle charging spaces (UDC 7.4.11.B.2). 5. COMMENT: 2-06.4.9.H.5.d – This comment was not addressed. Demonstrate compliance with all of UDC 7.4.9 relating to the proposed short- and long-term bicycle parking spaces. Provide details of the parking spaces as well. Refer to UDC Figures 7.4.9-A and 7.4.9-C. If you have any questions about this transmittal, please contact me at Wyatt.Berger@tucsonaz.gov or at (520) 837-4951. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/pdsd/website/Resubmittals.pdf. |
||
08/30/2023 | CDRC Application Completeness | REVIEW COMPLETED | |||
09/21/2023 | Fire New Construction | REVIEW COMPLETED | |||
09/28/2023 | Traffic Engineering Review | REVIEW COMPLETED | No Comments David Stiffey David.Stiffey@tucsonaz.gov |