Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: TD-DEV-0425-00097
Parcel: 11451200B

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.2

Permit Number - TD-DEV-0425-00097
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/19/2025 Commercial Plumbing Standard APPROVED
05/23/2025 NPPO Standard REQUIRES RESUBMIT Please see site landscape comments about the activity number. Once that activity number is added to the NPPO sheets, the NPPO will be approved.

Thank you.
Chad Keller, RLA
chad.keller@tucsonaz.gov
05/13/2025 ROW Engineering Review Standard REQUIRES RESUBMIT TD-DEV-0425-00097 • 8825 E TANQUE VERDE RD

1. Revise east driveway entrance to provide a standard driveway entrance with curb returns. Refer to drawing markups.

If you have any questions, please contact Richard Leigh at richard.leigh@tucsonaz.gov.
05/28/2025 Site Engineering Standard REQUIRES RESUBMIT 1. On the cover sheet please include the contact information (including name, address, email address, and phone number) for the firm that prepared the geotechnical report per Admin Manual section 2-06.4.1.
2. Include the waste stream calculations on the plans.
3. Include a detail of the trash enclosure to show compliance with Technical Standards Manual section 8-01.
4. Show onsite maneuverability for the trash vehicle to service the trash enclosure, turn around, and then exit the site.
5. Map Tucson is showing the southern portion of the site is within the critical basin mapped area of the Fahringer Wash, the drainage report states the site is not in critical basin. Revise as needed and demonstrate within the drainage report how the site is reducing the peak flow discharges for the 2, 10 and 100 year storm events by 15%.
6. Provide complete discussion, calculations, tables, and exhibits to establish accomplishment of first flush requirements. Include an exhibit comparable to Figure 2.1 in the Retention/Detention Manual that shows undisturbed area, disturbed area, impervious surfaces, non-contributing basins with landscape, stormwater harvesting basins including first flush, watershed #, stormwater harvesting basin #, and flow direction. Also include both tables 2.2 and 2.3 in the same section of the Retention/Detention Manual to demonstrate required/achieve retention volumes.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
05/23/2025 Site Landscape Standard REQUIRES RESUBMIT CDRC TRANSMITTAL
PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: DEVELOPMENT PACKAGE FOR A NEW CARWASH (ARTERIAL SCENIC COORIDOR)
ACTIVITY NO: TD-DEV-0425-00097
ADDRESS: 8825 E TANQUE VERDE RD
ZONING: C-1 COMMERCIAL
LAND USE: COMMERCIAL

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.

Please resubmit revised drawings along with a detailed response letter, which states how all of the Site Landscape and NPPO Section review comments have been addressed.

SITE LANDSCAPE/NPPO SECTION COMMENTS:

1. Add a construction detail or add to the section elevations on sheet L302 that depict how the berms interact with the riprap in the planting areas.

2. Provide the development package case number, TD-DEV-0425-00097, adjacent to the title block on all site landscape sheets, per Administrative Manual 2-06.4.3

3. Prior to Site Landscape Development Package approval, please make sure Site Zoning and Site Engineering comments are addressed.

Thank you.
Chad Keller, RLA
Landscape Architect
chad.keller@tucsonaz.gov
520.837.4923
05/20/2025 Site Zoning Standard REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Mister Car Wash - 8825 E TANQUE VERDE RD
Development Package (1st Review)
TD-DEV-0425-00097

TRANSMITTAL DATE: May 20, 2025

DUE DATE: May 15, 2025

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Per UDC Article 3.3.3.G.5.c, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is April 23, 2026.

2-06.4.0 CONTENT REQUIREMENTS

1. COMMENT: 2-06.4.1 – Provide the email addresses, and phone number of the primary property owner listed on the 1st sheet.

2. COMMENT: 2-06.4.3 – Provide the development package case number, TD-DEV-0425-00097, adjacent to the title block on all sheets.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

3. COMMENT: 2-06.4.7.A.3 – Ensure that the rezoning conditions listed on sheet 2 are the final conditions.

4. COMMENT: 2-06.4.7.A.3 - Provide the rezoning case number, TP-ENT-0124-00001, adjacent to the title block on all sheets.

5. COMMENT: 2-06.4.7.A.4 – As a general note identify the existing and proposed use of the property as classified per the UDC. List all UDC sections applicable to the proposed uses.

6. COMMENT: 2-06.4.7.A.6.a – As Tanque Verde Rd. is designated as an Arterial Scenic on the COT MS&R Map provide a general note on the cover sheet stating “THIS PROJECT IS DESIGNED TO MEET THE OVERLAY ZONE(S) CRITERIA, UDC ARTICLE 5.3 SCENIC CORRIDOR ZONE (SCZ) & UDC ARTICLE 5.4 MAJOR STREETS AND ROUTES SETBACK ZONE (MS&R)”.

7. COMMENT: 2-06.4.7.A.6.a – Clearly demonstrate that all requirements of UDC Article 5.3 are met.

8. COMMENT: 2-06.4.7.A.6.a – Provide the lot combination case number, TD-DIV-0525-00058, adjacent to the title block on all sheets.

2-06.4.7.A.8 - For development package documents provide:

9. COMMENT: 2-06.4.7.A.8.a – Provide the floor area for each building.

2-06.4.8 - Existing Site Conditions
The following information shall be provided on the plan/plat drawing to indicate the existing conditions on site and within 50 feet of the site. On sites bounded by a street with a width of 50 feet or greater, the existing conditions across the street will be provided.

10. COMMENT: 2-06.4.8.B – Clearly identify all existing easements on the plan and provide the recordation information. Any easements located with in the footprint of the building will need to be relocated or abandoned prior to approval of this DP.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

11. COMMENT: 2-06.4.9.E - As this site is made up of two (2) parcels, 114-51-200B & 114-51-200C the lot combination will need to be approved prior to approval of this DP.

12. COMMENT: 2-06.4.9.F - All existing zoning classifications on and adjacent to the project (including across any adjacent right-of-way) shall be indicated on the drawing with zoning boundaries clearly defined.

13. COMMENT: 2-06.4.9.H.5 – Provide a PAAL width dimension for the PAAL located between the vehicle parking spaces & vacuum stalls.

14. COMMENT: 2-06.4.9.H.5 – Provide an access lane width dimension for the southern most pay station access lane.

15. COMMENT: 2-06.4.9.H.5 – Provide a motor vehicle stacking calculation that provides the number of required and provided spaces.

16. COMMENT: 2-06.4.9.H.5 – Show the required motor vehicle stacking spaces on the plan, fully dimensioned.

17. COMMENT: 2-06.4.9.H.5.a – Provide a vehicle parking space calculation that provides the number of required and provide spaces to include standard, accessible & van accessible.

18. COMMENT: 2-06.4.9.H.5.a – Detail 1 sheet 6 the mounting height shown for the accessible sign is not correct. Mounting height requirements for accessible parking space sign shall be, 60” when wall mounted or 84” when located within a pedestrian circulation path

19. COMMENT: 2-06.4.9.O – Until comment 20 is addressed Zoning cannot determine front street perimeter yard setback requirements. Street setbacks shall meet the requirements of UDC Article 5.3.5.

20. COMMENT: 2-06.4.9.Q – Provide the square footage, height and the specific use proposed within the footprint of the building.

21. COMMENT: 2-06.4.9.R – Provide sidewalk width dimensions for all sidewalks shown on the plan.

22. COMMENT: 2-06.4.9.R – Based on detail 1 sheet 6, parking vehicles will be allowed to overhang the sidewalk along the south side of the proposed building. Clearly demonstrate that a parking vehicle will not reduce the sidewalk to less than 4’-0” wide. Minimum sidewalk width required when parking vehicles are allowed to overhang the sidewalk is 6’-6’, TSM Section 7-01.4.3.A minimum width 4’ plus UDC Article 7.4.6.H.3 2’-6” overhang equals 6’-6” wide sidewalk.

23. COMMENT: 2-06.4.9.U - Indicate graphically, where possible, compliance with conditions of rezoning.

24. COMMENT: 2-06.4.9.W - Indicate the locations and types of proposed signs (wall, free-standing, pedestal) to assure there are no conflicts with other requirements and that minimal locational requirements can be met.

25. COMMENT: 2-06.4.9.W – Provide a general note stating all signage requires separate permits.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf.
04/24/2025 CDRC Review Coordinator Express REVIEW COMPLETED CDRC added TEP, PAG, USPS, and SWG to the workflow. Review request email sent to TEP. FYI email sent to PAG, USPS, SWG.
04/29/2025 External Reviewers - Pima Association of Governments Standard REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
04/29/2025 External Reviewers - Southwest Gas Standard REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
05/13/2025 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED May 13, 2025
WO#T149681
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Mister Carwash - Bear Canyon
TD-DEV-0425-00097
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 04/24/2025. There are existing facilities within the development, which
are depicted upon the plan. Please refer to the attached recorded instrument, Docket
11779 Page 3293, for existing underground segment.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
Martin Rodriguez
(520) 991-5495
mrodriguez@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
04/29/2025 External Reviewers - United States Postal Service (USPS) Standard REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
05/14/2025 Fire New Construction Standard REVIEW COMPLETED
04/24/2025 OK to Submit - Zoning Fast REVIEW COMPLETED