Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Approved
Review Details: DEVELOPMENT PACKAGE NEW v.1
Permit Number - TD-DEV-0324-00097
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Approved
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/29/2024 | Commercial Plumbing | APPROVED | |||
04/26/2024 | Site Engineering | APPROVED | |||
04/29/2024 | Site Zoning | APPROVED | |||
05/08/2024 | NPPO | NOT REQUIRED | |||
05/08/2024 | Site Landscape | NOT REQUIRED | |||
03/22/2024 | CDRC Application Completeness | REVIEW COMPLETED | |||
05/09/2024 | CDRC Post Review | REVIEW COMPLETED | |||
04/02/2024 | CDRC Review Coordinator | REVIEW COMPLETED | Review request email sent per ADOT. CDRC sent FYI email to PAG, USPS, SWG and TEP. | ||
05/03/2024 | External Reviewers - Arizona Department of Transportation (ADOT) | REVIEW COMPLETED | Good Afternoon, ADOT has no comments on this DEV. Thank you for the opportunity to review. | ||
04/02/2024 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
04/02/2024 | External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
04/02/2024 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
04/02/2024 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
04/08/2024 | Fire New Construction | REVIEW COMPLETED | |||
03/26/2024 | OK to Submit - Engineering | REVIEW COMPLETED | |||
03/25/2024 | OK to Submit - Landscape | REVIEW COMPLETED | |||
03/28/2024 | OK to Submit - Zoning | REVIEW COMPLETED | |||
04/29/2024 | ROW Engineering Review | REVIEW COMPLETED | No Comments David Stiffey David.Stiffey@tucsonaz.gov |