Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE REVIEW v.1
Permit Number - TD-DEV-0223-00144
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/06/2023 | CDRC Post Review | PENDING ASSIGNMENT | |||
03/06/2023 | CDRC Review Coordinator | PENDING ASSIGNMENT | |||
03/06/2023 | Commercial Plumbing | PENDING ASSIGNMENT | |||
03/06/2023 | Fire New Construction | PENDING ASSIGNMENT | |||
03/06/2023 | NPPO | PENDING ASSIGNMENT | |||
03/06/2023 | ROW Engineering Review | PENDING ASSIGNMENT | |||
03/06/2023 | Site Engineering | PENDING ASSIGNMENT | (Please note, I am reviewing the drainage report for all phases as that is how the drainage report is laid out, but other site comments should be provided on the phase 1 plan. All phase 1 compliancy requirements outlined below must be provided during construction of phase 1.) 1. Show how roof drainage up to the 10-yr storm will be directed away from/under adjacent sidewalks through the use of gutters/scuppers 2. Drainage Report: Label Basin top elevation, ensure 6" freeboard from 100-yr WSEL (12" with embankment) 3. Drainage Report: Water Harvesting Basin labelled as "1-ft deep," ensure 9" maximum of retention depth is provided, unless a perc test showing adequate infiltration at higher depths is provided 4. Drainage Report: Show attenuation of 2-yr developed discharge due to the water harvesting basin. This should mostly attenuate the pre vs post difference in 2-yr discharge along 12th, any leftover we will waive. 5. Drainage Report: Each phase must have its retention/detention broken down and accounted for at time of construction. The entire site can be calculated as done currently, but the improvements must then be built in the first phase to attenuate its requirements 6. A SWPPP and ADEQ dust permit will be required for all phasing. See ADEQ website for details https://azdeq.gov/AZPDES/SWPPP 7. Dumpster enclosure not to COT standard, ensure all design standards found in TSM 8-01 are followed 8. Clearly delineate current and proposed parking lot and parking spaces as planned for phase 1. Show proper waste vehicle maneuverability and access to and from waste enclosure (TSM 7-01) 9. Show a pedestrian circulation path to both Calle Alvord and S 12th Ave, as well as to the planned waste enclosure from all buildings (TSM 7-01) 10. Show vertically separated sidewalk between existing structure and any adjacent PAALs or parking spaces (TSM 7-01) 11. Include a note that any sidewalks should have 2% max cross slope, 5% max running slope, and that any ramps should have 8.3% max slope (Full review pending) Scott Haseman scott.haseman@tucsonaz.gov |
||
03/06/2023 | Site Landscape | PENDING ASSIGNMENT | |||
03/06/2023 | Site Zoning | PENDING ASSIGNMENT | |||
03/03/2023 | OK to Submit - Engineering | REQUIRES RESUBMIT | A SWPPP is required for the proposed master plan, which will need to be active for each phase. See SWPPP requirements at https://azdeq.gov/AZPDES/SWPPP Scott Haseman scott.haseman@tucsonaz.gov |
||
03/06/2023 | OK to Submit - Zoning | REQUIRES RESUBMIT | 1. Address Engineering comments. Loran Shamis |
||
02/28/2023 | CDRC Application Completeness | REVIEW COMPLETED | |||
03/02/2023 | OK to Submit - Landscape | REVIEW COMPLETED |