| 07/31/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 07/13/2023 | Residential Building | REQUIRES RESUBMIT | Permit Review Rev3 TC-RES-0323-03447 (3325 N FORGEUS AV TUCSON, AZ 85716) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2018 International Residential Code (IRC). Comments that were not addressed: 1. Show Bathroom receptacles with a separate 20 AMP dedicated circuit, E3703.4 and E3901.6. Electrical plans show the bathroom outlets as 15A. 2. Provide a landing or floor surface at all exterior doors. A landing must be at least as wide as the door it serves and 36” in the direction of travel, R311.3. Remove the “Future” notation from the Foundation Plan on Sheet 2 relative to the Stoops. 3. Show or notate, all outdoor receptacles as GFCI protected, E3902.3. Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov |
||
| 07/05/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-RES-0223-03447 3325 N Forgeus Av. - R-1 Detached Accessory Structure (3rd Review) TRANSMITTAL DATE: July 05, 2023 COMMENT: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Zoning acknowledges the submittal of the DDO application but until the DDO is approved and comment 2 is addressed Zoning cannot approve these plans. 1. This comment was not addressed. Perimeter yard setbacks have been measured from design grade since the approval of the Land Use Code in 1995. Perimeter yard setbacks are based on a measurement from design grade to the highest point of the exterior wall UDC Article 6.4.5.B & Figure 6.4.5-A. Based on a wall height of 9’-4” for the wall adjacent to the west property line the required perimeter yard setback from the proposed structure to the west property line is 6’-3”, proposed setback is 6’-0”. The reduced perimeter yard setback can be dealt with in one of two ways: 1) Per UDC Article 6.6.2.D An accessory structure that exceeds the allowable height of a wall within a perimeter yard and is detached from a principal structure shall comply with the perimeter yard width standards of the principal structure, except that the accessory structure may be built to a parcel line with the consent of the adjoining or, when separated by an alley, adjacent property owner(s). To secure this neighbor setback waiver the following statement must be provided on the plot plan and be signed and dated by the adjacent property owner(s): My Name is____________________ and I am the owner of the property located at _______________________. I have reviewed the site plan and I have no objection to structure being located or constructed________ feet from the property line as depicted on the site plan. Signature: _____________________________ Date: ________________________________ 2) Include the perimeter yard setback in the Design Development Option (DDO) required for the wall height as stated below. COMMENTS: the following comments are relative to an application for a Design Development Option (DDO) (UDC 3.11.1). 3. The maximum height of a wall or fence within a perimeter yard shall be six (6) feet (UDC Section 6.6.2.I). The maximum height of a retaining wall is ten (10) feet from design grade and no higher than six (6) feet measured from the top of the retaining portion of the wall (UDC Section 6.6.2.I.2). A Design Development Option (DDO) must be submitted and approved for the proposed wall height, DDO application and requirements can be found at: https://www.tucsonaz.gov/files/pdsd/forms/DDO_for_Setback_and_Height_UDC_8.11.20.pdf. If you have questions about the DDO application or process please contact Mark Castro at Mark.Castro@tucsonaz.gov. 2. This comment was not addressed. Zoning is not requesting approval to access the easement. You are required to submit letters from all utilities that have access rights to the easement, i.e. TEP, Southwest Gas etc. As the proposed wall is located within the 5’-0” utility easement, provide written approval allowing the wall within the easement from all utilities who have rights to this easement. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
| 07/31/2023 | Zoning Modifications - DDO | REQUIRES RESUBMIT | FROM:Georgia Pennington, Planner DATE: 7/31/23 COMMENTS: 1. This comment from Site Zoning must be addressed prior to DDO processing: "Zoning is not requesting approval to access the easement. You are required to submit letters from all utilities that have access rights to the easement, i.e. TEP, Southwest Gas etc. As the proposed wall is located within the 5’-0” utility easement, provide written approval allowing the wall within the easement from all utilities who have rights to this easement." 2. Include the wall height increase request in your DDO application request. If you have questions about this transmittal, please email me at georgia.pennington@tucsonaz.gov. |
||
| 06/28/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |