Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-1225-02185
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/05/2026 | Site Engineering Standard | APPROVED | |||
| 01/05/2026 | Site Zoning Standard | APPROVED | Associated DP (TD-DEV-0725-00182) has been approved. | ||
| 01/05/2026 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 12/26/2025 | Commercial Building Standard | REQUIRES RESUBMIT | Please submit your revised documents and provide a letter with a written response letter addressing each of the comments indicating how the Review comments were resolved. Additionally, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please note the submittal was incomplete and the plan review was conducted using the information presented. The subsequent review could generate more comments after original comments have been addressed. 1. Please amend architectural wall sections at foundations to clearly show the curb raising the framing 4” above the finish floor. IBC 107.2.1 2. Provide the signed and sealed structural calculations, prepared by an Arizona licensed registrant, used in the design of this project. IBC 107.2.7 to include light pole foundations. 3. Please amend the plans to provide a project specific statement of special inspections for this project, stating requirements for the special inspections and required tests. IBC 107.2.1, IBC 1704, IBC 1705 and print the tables on the plans. Additionally, provide the City of Tucson Special Inspection Certificate(s) with Parts A and B completed with the next submittal. IBC 107.1 SI form link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate.pdf 4. Please provide the Soils Report used in the design of the foundation with next submittal. IBC 107.2.1 Please contact me if you have any questions about these comments. Mark Masek Plans Examiner – Building Safety Planning and Development Services | City of Tucson main 520.837.4994 email mark.masek@tucsonaz.gov |
||
| 12/19/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | Commercial Electrical Review TC-COM-1225-02185 (10100 E OLD VAIL RD TUCSON, AZ 85747) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2018 International Building Code (IBC), 2017 National Electrical Code (NEC). 1. Provide an updated Electrical site plan showing the estimated locations of all electrical equipment, including the new utility transformer. 2. Show the estimated location of all electrical lines, underground and overhead, and conduits to all equipment, including the connection to the service entrances of each building. Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov |
||
| 12/30/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | 1. If the gravity grease interceptor is being installed as part of the shell building, provide the sizing calculations for the gravity grease interceptor and show the grease waste piping from the building to the interceptor and the downstream vent for the interceptor. Reference: Section 1003.3, IPC 2018, as amended by the City of Tucson. 2. Provide roof drainage calculations based on the 100-year hourly rainfall rate for Tucson, 3” per hour. Provide the size of the stormwater conductors. Reference: Sections 1101.7, 1106, and 1108, IPC 2018. |
||
| 12/18/2025 | Outdoor Lighting Standard | REQUIRES RESUBMIT | Outdoor Lighting Review TC-COM-1225-02185 (10100 E OLD VAIL RD TUCSON, AZ 85747) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2018 International Building Code (IBC), 2017 National Electrical Code (NEC), 2012 Outdoor Lighting Code (OLC). Outdoor Lighting Review: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/building-code/2012_outdoor_lighting_code_.pdf a. Provide an outdoor site lighting plan that meets the requirements of OLC 104.2. Show/locate the different light sources on your site plan. Number the light fixtures on your lighting fixture table and use the same number on your site plan. This will require all exterior lights to be shown on the site exterior lighting plan, including site and parking lot lights. b. List the Lighting Area per OLC (typically E3) chapter 3 and used in Table 401.1. Specify the compliance option from Table 401.1 that is being used. Total outdoor light output shall not exceed the lumen limits listed in Table 401.1. c. Show compliance with City of Tucson Outdoor Lighting Code with an approved lighting calculation in accordance with OLC 104.2.1, 401.2. Include all exterior fixtures on the property in the calculations. List shielded and unshielded lights in the calculation. d. Show unshielded fixtures with a maximum of 3,000 lumens, OLC 401.4. e. Show lamps with a maximum of 3500K color temperature, OLC 402.1. f. Provide the manufacturer’s specification sheets for the outdoor lighting fixtures. Include the lumen and color temperature values for each outdoor fixture type. g. Indicate whether or not a special inspection is required per sec. 104.2.2, and 106.2. https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate_odl.pdf h. Specify any exceptions used. i. Provide Curfew lighting controls If applicable Per section 403. Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov |
||
| 12/30/2025 | Water - PDSD Standard | REQUIRES RESUBMIT | Remove or correct detail 3/P101. Installation of the water meter is to be 3’ from the property line, in the right of way (see Tucson Water Standard Detail SD-309). Reduced pressure backflow prevention assemblies are required to be installed directly after the water meter for buildings that have food service facilities; outside, above ground, and on private property (see Tucson Water Standard Detail SD-1802). | ||
| 12/30/2025 | Commercial Mechanical Standard | REVIEW COMPLETED | |||
| 12/31/2025 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 12/09/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |