Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-1224-02366
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/04/2025 | Commercial Building | APPROVED | Structural(S) Reviewer (from previous submittal TUC9642001.122324) Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 1/5/2025 10:57:58 PM Building(B) Reviewer Kimiyoshi Shimabukuro kshimabukuro@safebuilt.com Approved with Comments Reason: Date Completed : 5/31/2025 3:50:58 AM |
||
| 06/04/2025 | Commercial Electrical | APPROVED | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 5/30/2025 4:09:50 PM |
||
| 06/04/2025 | Commercial Plumbing | APPROVED | Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved Reason: Date Completed : 6/1/2025 12:54:26 PM |
||
| 06/04/2025 | Outdoor Lighting | APPROVED | Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 5/30/2025 4:09:50 PM |
||
| 06/04/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 06/04/2025 | Commercial Mechanical | REQUIRES RESUBMIT | Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Denied Reason: Date Completed : 6/4/2025 10:50:29 AM 1. (UNRESOLVED) - General - How is Ventilation provided? Specify on the drawings the outdoor air required by the 2018 IMC Section 403.3.1.1 Substantiate compliance by providing calculations on the drawings which indicates the floor area (sq. ft), maximum occupant load, minimum required ventilation rate (cfm) for each occupancy, and total ventilation rate provided to the occupied space. Separate calculations by unit types. i. Provide method of Ventilation. How is O/A provided. Specify on the drawings the outdoor air required by the 2018 IMC Section 403.3.1.1 Substantiate compliance by providing calculations on the drawings which indicates the floor area (sq. ft), maximum occupant load, minimum required ventilation rate (cfm) for each occupancy, and total ventilation rate provided to the occupied space. Separate calculations by unit types. 2. (RESOLVED) - General - Provide COMcheck Mechanical Compliance Certificate. Any other APPROVED certifying agency can be submitted. - 2018 IECC Section C403.3.2 HVAC equipment performance requirements. 3. (RESOLVED) - General - As stated in #1 of the Key Notes on Plan Sheet M1.1 CONNECT TO EXISTING DUCTWORK, CONDENSATE DRAIN AND REFRIGERANT LINES IN CEILING SPACE. CONTRACTOR TO FIELD VERIFY EXACT SIZE,LOCATION AND WORKING CONDITIONS BEFORE START OF WORK. (When and if applicable) Any and all replacement of duct work must be included in a mechanical review. Plan Review 6/4/2025 1. Plan Sheet A2.3.2 shows a laundry room which was not included in the Mechanical plans. Provide a detail on the Mechanical plans of the laundry room. Show all dryer exhaust ducts to exterior of building with makeup air and if applicable combustion air. Note #10 on the General Notes states "REPLACE HVAC EQUIPMENT: REMOVE AND REPLACE SPLIT SYSTEM; REMOVE AND REPLACE BATH FAN. UTILIZE EXISTING DUCTS, AND INSTALL NEW PROGRAMMABLE THERMOSTATS." - 2018 IECC Section C103.2Information on construction documents. - 2018 IBC Section [A]107.2.1Information on construction documents. 2. Plan Sheet A2.3.3 shows a Community Kitchen which was not included in the Mechanical Plans. Provide a detail on the Mechanical plans showing all exhaust from all kitchen ranges/stoves. Note #10 on the General Notes states "REPLACE HVAC EQUIPMENT: REMOVE AND REPLACE SPLIT SYSTEM; REMOVE AND REPLACE BATH FAN. UTILIZE EXISTING DUCTS, AND INSTALL NEW PROGRAMMABLE THERMOSTATS." - 2018 IECC Section C103.2Information on construction documents. - 2018 IBC Section [A]107.2.1Information on construction documents. |
||
| 05/29/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |