Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-1123-02690
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
12/27/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
12/26/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 12/22/2023 11:06:23 AM Building(B) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 12/21/2023 11:19:23 AM 1) Resolved - General: Provide the drawings, dimensions, distance to the ceiling, and specification/installation sheets of the racking. (2018 IBC section 107) 2) Resolved - General: Include the building thermal envelope details showing compliance with the 2018 IECC for the newly heated spaces. (2018 IECC section C402) 3) Unresolved - Sheet A0.0: Provide a description of the items being manufactured and the processes performed. Include the materials/items stored, quantity and location of chemicals stored or used, MSDS sheets of the chemicals, etc. to determine if a hazardous use is present. (2018 IBC section 107, 307, 414) Provide this information on the drawings. Include the allowed vs actual amounts of chemicals stored and location of the storage cabinet. 4) Resolved - Sheets A0.0, A2.1: Show the floor areas used in the occupant load calculations. The office, industrial, and warehouse areas are to include the corridor, walls, closets, etc. as defined for gross floor area. The office spaces are to be calculated at 1 person per 150sf gross, industrial at 1 per 100sf gross, and warehouse 1 per 300 sf gross. The assembly areas appear to have been calculated correctly at 1 per 15sf net area. Please revise all affected sheets. (2018 IBC section 1004, Table 1004.5) 5) Unresolved - Sheets A2.1, A2.2: Show the accessible turning space in the women's toilet room and the toilet clear floor spaces and dimensions in both toilet rooms. Include the distance of the toilet center line to the side walls and drinking fountain accessibility details. (2009 ICC A117.1 sections 304.3, 602, 603) Toilet clear floor spaces and drinking fountain accessibility details were not provided. 6) Unresolved - Sheet A2.1: Show the means of egress travel distance from the most remote point in the center of the warehouse racking rows. Verify the means of egress emergency lighting of the paths is not blocked by the high piled storage racking. (2018 IBC section 1017.3, 1008.3) The paths shown are not the longest paths from the most remote locations in the middle of the racking area to the exits. Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Denied Reason: Date Completed : 12/21/2023 9:46:38 AM 1. General - Provide Ventilation Calculation/Schedule - 2018 IMC Section Table 403.3.1.1 - 2018 IECC C403.2.2 (RESOLVED) 2. Provide plans for spray booths. Provide manufacturer specifications. Show location of spray booths. Show Make up air openings and quantities - 2018 IMC Section 502 Required Systems (UNRESOLVED) i. Provide Mechanical Plans for owner provided/installed spray booths. Provide manufacturer specifications. Show location of spray booths. Show Make up air openings and quantities. Show all supply and exhaust duct work. If applicable Show all compressed air and lines. Show air compressor. - 2018 IMC Section 502 Required Systems - 2018 IBC – Section [A]107.2.1Information on construction documents. 3. Provide Commercial Energy Calculations/Mechanical compliance Certificate - Heat Loads - 2018 IECC Section C403 Building Mechanical Systems - 2018 IECC Section C402 Building Envelope Requirements (UNRESOLVED) i. Mechanical compliance Certificate not included in submittal. - 2018 IECC Section C403 Building Mechanical Systems - 2018 IECC Section C402 Building Envelope Requirements. Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 12/21/2023 2:22:37 PM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 12/25/2023 4:32:22 PM Second Plumbing Review: Unresolved-1), Need to address bldg. plan review comment 5 -IPC 403.1, 404.2 Resolved 2). add gas system legnth & sizing table used to plan page P1.1 -IFGC 402.3 Resolved 3). Janitor Sink & adjacent Floor drain vents can't horizontally offset below flood rim of fixture - IPC 905.4 |
||
12/27/2023 | Fire New Construction | REVIEW COMPLETED | |||
12/20/2023 | PDSD Application Completeness | REVIEW COMPLETED |