Permit Number: TC-COM-1123-02690
Parcel: 140411250

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-1123-02690
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/04/2023 Site Zoning APPROVED
12/12/2023 Water - PDSD APPROVED
12/15/2023 Site Engineering NOT REQUIRED
12/15/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
12/07/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 12/5/2023 1:49:19 PM
1. GENERAL - UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.

2. GENERAL - GEOTECHNICAL REPORT: Please provide a copy of the site-specific geotechnical report for this project. The report should reflect the allowable net bearing pressure listed on the structural general notes, and all building code references must be updated to the current code adopted by the City. As an alternative, the scope of this project allows for the use of the presumptive load bearing values from 2018 IBC Table 1806.2. If the engineer's intention is to utilize these values, please revise the structural general notes to reflect the allowable bearing pressure for "sand, silty sand, clayey sand, silty gravel and clayey gravel" (2,000 psf) in lieu of submitting a formal geotechnical report.

3. M1.2 - MECHANICAL LOADS: Mechanical roof plan, M1.2, references equipment on the roof ranging from 850 lb to 2,100 lb. Please coordinate locations and weights of these Mechanical units and verify that the existing roof framing is sufficient to support the new mechanical loads. If reinforcement of the existing roof joists is needed, please provide a structural roof plan and details.

4. A0.1 - SITE STRUCTURES: Architectural Drawing A0.1 indicates a new trash enclosure with concrete foundation and CMU walls "per structural". Please provide the necessary design information for any site structures, including foundation elements, concrete and masonry reinforcing and relevant masonry details.




Building(B) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 11/30/2023 10:23:09 AM
1) General: Provide the drawings, dimensions, distance to the ceiling, and specification/installation sheets of the racking. (2018 IBC section 107)

2) General: Include the building thermal envelope details showing compliance with the 2018 IECC for the newly heated spaces. (2018 IECC section C402)

3) Sheet A0.0: Provide a description of the items being manufactured and the processes performed. Include the materials/items stored, quantity and location of chemicals stored or used, MSDS sheets of the chemicals, etc. to determine if a hazardous use is present. (2018 IBC section 107, 307, 414)

4) Sheets A0.0, A2.1: Show the floor areas used in the occupant load calculations. The office, industrial, and warehouse areas are to include the corridor, walls, closets, etc. as defined for gross floor area. The office spaces are to be calculated at 1 person per 150sf gross, industrial at 1 per 100sf gross, and warehouse 1 per 300 sf gross. The assembly areas appear to have been calculated correctly at 1 per 15sf net area. Please revise all affected sheets. (2018 IBC section 1004, Table 1004.5)

5) Sheets A2.1, A2.2: Show the accessible turning space in the women's toilet room and the toilet clear floor spaces and dimensions in both toilet rooms. Include the distance of the toilet center line to the side walls and drinking fountain accessibility details. (2009 ICC A117.1 sections 304.3, 602, 603)

6) Sheet A2.1: Show the means of egress travel distance from the most remote point in the center of the warehouse racking rows. Verify the means of egress emergency lighting of the paths is not blocked by the high piled storage racking. (2018 IBC section 1017.3, 1008.3)




Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Denied
Reason:
Date Completed : 12/1/2023 6:54:19 PM
1. General - Provide Ventilation Calculation/Schedule - 2018 IMC Section Table 403.3.1.1 - 2018 IECC C403.2.2

2. Provide plans for spray booths. Provide manufacturer specifications. Show location of spray booths. Show Make up air openings and quantities - 2018 IMC Section 502 Required Systems

3. Provide Commercial Energy Calculations/Mechanical compliance Certificate - Heat Loads - 2018 IECC Section C403 Building Mechanical Systems - 2018 IECC Section C402 Building Envelope Requirements



Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 12/2/2023 6:21:00 PM
Electrical Review of Tucson Commerce Center
By: Ron Ross PE
E1.1 Overall Plan – Lighting: Could not locate Keyed Note 1.

E1.2 Enlarged Plans - Lighting: Office area needs an interior lighting comcheck.

E2.2 Enlarged Plans - Power:

Need to provide size of conductors and conduit for all circuits larger than 20 amps.

Need to identify circuits to disconnects and coordinate with E3.1 panel schedules.
E3.1 Panel Schedules:

Need to call out conductor count and size on secondary side of 75 KVA transformer.

Need to call out conductor size for all circuits greater than 20 amps, either on panel schedule or on sheet E2.2.



Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 12/6/2023 9:43:55 PM
First Plumbing Review:
1), Need to address bldg. plan review comments 4 & 5 -IPC 403.1, 404.2

2). add gas system legnth & sizing table used to plan page P1.1 -IFGC 402.3

3). Janitor Sink & adjacent Floor drain vents can't horizontally offset below flood rim of fixture - IPC 905.4
12/15/2023 Fire New Construction REQUIRES RESUBMIT Address Safebuilt comments.
Questions: patricia.shelton@tucsonaz.gov
11/21/2023 PDSD Application Completeness REVIEW COMPLETED