Permit Number: TC-COM-1122-00161
Parcel: 141114050

Review Status: Requires Resubmit

Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1

Permit Number - TC-COM-1122-00161
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
03/26/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
03/26/2025 Concrete Installation Inspection (Deferred Submittal) Express REQUIRES RESUBMIT 1. Multiple Special inspection certificate's submitted, the permit is for Building 10, we cannot approve a submission with building 9, that needs to be a separate permit.
2. Remove inspections that are not being utilized, N/A is not acceptable.
3. Fill out part A of the Special Inspection Certificate. Please re submit.
03/26/2025 Other Inspection Reports (Deferred Submittal) Express REQUIRES RESUBMIT 1. Multiple Special inspection certificate's submitted, the permit is for Building 10, we cannot approve a submission with building 9, that needs to be a separate permit.
2. Remove inspections that are not being utilized, N/A is not acceptable.
3. Fill out part A of the Special Inspection Certificate. Please re submit.
03/26/2025 Post-Installed Anchor Inspection (Deferred Submittal) Express REQUIRES RESUBMIT 1. Multiple Special inspection certificate's submitted, the permit is for Building 10, we cannot approve a submission with building 9, that needs to be a separate permit.
2. Remove inspections that are not being utilized, N/A is not acceptable.
3. Fill out part A of the Special Inspection Certificate. Please re submit.
03/26/2025 Welding Inspection (Deferred Submittal) Express REQUIRES RESUBMIT 1. Multiple Special inspection certificate's submitted, the permit is for Building 10, we cannot approve a submission with building 9, that needs to be a separate permit.
2. Remove inspections that are not being utilized, N/A is not acceptable.
3. Fill out part A of the Special Inspection Certificate. Please re submit.
03/24/2025 PDSD Application Completeness Express REVIEW COMPLETED