Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - LIMITED v.1
Permit Number - TC-COM-1024-02027
Review Name: COMMERCIAL REVIEW - LIMITED v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/04/2024 | Water - PDSD | APPROVED | |||
11/06/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
11/06/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved Reason: Date Completed : 11/6/2024 1:01:01 PM Building(B) Reviewer Keith Miller kmiller@safebuilt.com Denied Reason: Date Completed : 11/5/2024 9:55:57 AM 1. Special Inspection Certificate: Include all special inspection categories as specified in the plans and list the specific approved special inspector for each inspection category. (2018 IBC section 1704) 2. General: The architect’s seal may not be legible on many sheets in the set. Verify that the seals are legible when the pages are printed. (2018 IBC section 107) 3. Sheet G100: The wall insulation and fenestration values listed do not match the R-value and U-Factor specified in the Home Energy Rating Certificate. Please correct and coordinate all affected sheets and details. (2018 IECC section C402) 4. Sheets G100, G101: Include the total occupant load. (2018 IBC section 107) 5. Sheet A601: Include the hardware set details and U-Factors in the door schedule. (2018 IBC section 107) 6. Sheet A602: Include the U-Factor, SHGC, and safety glazing of the windows in the window schedule. Coordinate entries with the Home Energy Rated Certificate entries. (2018 IBC section 107) 7. Sheets G101, E302, E303, E304: Include the emergency lighting and exit signs along the means of egress travel path. The exit signs in the elevator lobby on levels 2, 3, and 4 do not show the exit sign at the exit stair entrance. (2018 IBC sections 1008.3, 1013.1) Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 11/4/2024 12:05:30 PM Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 10/29/2024 6:03:00 PM 1. E104 panel schedule names 1HP, 2HP, 3HP, and 4HP do not match Schematic Feeder Wiring Diagram. Should correct/coordinate for Construction set. 2. E200 need to provide site lighting calculation to show compliance with Tucson City ordinance. 3. E201comment only concerning Keynote 14. Isn’t 12 inch height above pit floor too low for lighting ie 36-48 inches may be more appropriate. 4. E202 Could not locate Keynote 1 and missing Keynote #5. Elevator Keynotes may not be needed for upper floors. 5. E205 is missing from set. Remove from sheet index if not needed. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 11/5/2024 9:10:33 PM First Plumbing Review: 1). Plan Page P201: Waste Stacks 4 & 5 can't reduce in size in the direction of flow. Stacks 4 & 5 need to be 3" in its entirety from floor to roof. -2018 IPC 704.2 & 913.4 2). Plan Page P202: Waste Stacks 3 & 4 are undersized. Waste stacks 3 & 4 Need to be a minimum of 3" - 2018 IPC 913.4 3). General Plumbing plans: Missing Typical living units water piping plans. Add Typical living units water piping plans. -2018 IPC 106.3.1 4). Plan Page P203: Missing common area restrooms & community room water piping riser. Add common area restrooms & community room water piping riser. -2018 IPC 106.3.1 5). Plan Page P001: Common area lavatoty info missing ASSE 1070 Mixing Valves. Add required mixing valve info to Common area lavatory info on fixture schedule. -2018 IPC 419.5 6). Plan Page A400: Missing fixture spacing measurements for lavs & toilets. Add fixture spacing measurements. -2018 IPC 404.2, 405.3.1 |
||
11/05/2024 | Fire New Construction | REQUIRES RESUBMIT | -Add the following note as indicated in presub notes: Building to be tested for Emergency Responder Communication Enhancement System. Testing to be completed by PCWIN and report provided to TFD. ERCES shall be installed depending on test results. -Roof access is required for the 4th story roof. The current roof access is only to the 3rd story roof. Will you provide a ladder on the roof from the 3rd story to the 4th story at the elevation change? IFC 504.3 john.vincent@tucsonaz.gov 5203495581 |
||
11/04/2024 | Site Engineering | REQUIRES RESUBMIT | 1. The associated development package TD-DEV-0724-00202 must be approved before this building permit can be approved. Mike Ortiz michael.ortiz@tucsonaz.gov |
||
11/04/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: Loran Shamis PDSD Zoning Review Section PROJECT: TC-COM-1024-02027 Multifamily Development 1910 N Stone Avenue TRANSMITTAL DATE: November 4, 2024 DUE DATE: November 5, 2024 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Ensure the building plans are consistent with the Development Package, TD-DEV-0723-00202 as it relates to the zoning review purview of the Building footprint, Height, square footage, site conditions etc., Zoning cannot approve the building plans until the PDSD Commercial Plans reviewers have approved the building plans. Once the plans have been reviewed and approved by PDSD Commercial Plan Reviewers and Zoning has verified consistency with the DP, the building plans can be approved by Zoning. If you have any questions about this transmittal, Contact Loran Shamis at 520-837-2242 or by email Loran.Shamis@tucsonaz.gov |
||
10/22/2024 | PDSD Application Completeness | REVIEW COMPLETED |