Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0926-01563
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/02/2026 | Commercial Electrical Standard | APPROVED | |||
| 10/12/2026 | Commercial Mechanical Standard | APPROVED | |||
| 10/12/2026 | Commercial Plumbing Standard | APPROVED | |||
| 10/02/2026 | Outdoor Lighting Standard | APPROVED | |||
| 10/12/2026 | Water - PDSD Standard | APPROVED | |||
| 10/13/2026 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 10/12/2026 | Commercial Building Standard | REQUIRES RESUBMIT | Please submit a complete set of revised/corrected documents and a written response addressing each review comment and explaining how it was resolved. Please note that the original submittal was incomplete, and the review was based on the information provided. Additional comments may be issued upon subsequent review. Please contact me if you have any questions about the below comments. I can be reached at email mark.masek@tucsonaz.gov 1. Please show compliance with 2024 IECC C402.4 per Table C402.3 Indicate the color of the TPO roof, provide the SRI values and provide the manufacturer’s spec sheet. 2. Please show the required air-barrier documentation requirements required by 2024 IECC C402.6.1.1 3. Please indicate the whole building thermal envelope test method and reporting to be used for this project in compliance with 2024 IECC C402.6.2.13. 4. Provide the applicable ICC Evaluation Service (ICC-ES) Evaluation Report (ESR), or equivalent approved evaluation report, for the proposed stucco/EIFS assembly and air/water-resistive barrier system. The report shall identify the proposed products, installation requirements, and applicable limitations. 2024 IBC Sections 104.11, 1403.2, and 1404.2, as applicable. A. Provide a special Inspections schedule to identify inspections required by the applicable evaluation report and 2024 IBC Section 1705.17, where applicable, for EIFS and liquid-applied air/water-resistive barrier systems. Identify the applicable inspection requirements and frequency in accordance with the approved evaluation report and construction documents. Please contact me if you have any questions about the above comments. Mark Masek Plans Examiner – Building Safety Planning and Development Services | City of Tucson main 520.837.4994 |
||
| 10/13/2026 | Fire New Construction Standard | REQUIRES RESUBMIT | -Door #110 shows an exit sign above it that is visible from the lobby. (floor plan and electrical sheets). Is this door considered a required exit from the lobby? Sheet a1.0 states it is for staff only and is equipped with a lockset per the door schedule. Resolve exiting issue. Provide new occupant load of the lobby space only if there will be only one exit provided for this space. john.vincent@tucsonaz.gov 5203495581 |
||
| 09/25/2026 | Site Engineering Standard | REQUIRES RESUBMIT | Reviewer: John Mounsey – Engineering Associate Reviewer Contact Information: john.mounsey@tucsonaz.gov Site Engineering Comments: 1. Site Engineering has completed its review of the submitted plan set and cross-referenced it against the associated development package. However, Site Engineering is unable to grant final approval for Commercial Permit: TC-COM-0926-01563 until the associated revision to Development Package TD-DEV-0726-00199 has received full approval and has been issued. Please resubmit for final approval once the development package has been approved and issued by all applicable reviewers. For final approval - Ensure that all building plans match in regard to footprint, proposed height and square footage with what is shown in the development package plan set. |
||
| 10/12/2026 | Site Zoning Standard | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: Jeffrey W. Cassidy, Planner I Planning & Development Services Department – Current Zoning Review Section, Commercial PROJECT: TC-COM-0926-01563 – Commercial – New Credit Union with drive-thru 9915 E OLD VAIL RD TUCSON, AZ 85747 (I-1 Zoning) Commercial Building Plan Review – 1st Review TRANSMITTAL DATE: October 12, 2026 1. COMMENT: Zoning has completed its review of the submitted building plan set and cross-referenced it against the associated Development Package. However, final approval of Commercial Permit TC-COM-0926-01563 cannot be granted until the associated revision to Development Package TD-DEV-0726-00199 has received full approval and has been issued. Per UDC §3.3.3.G, building permits for sites requiring a Development Package may not be issued prior to DP approval, as the building plans must be consistent with an approved site plan. Please resubmit for final approval once the Development Package has been approved and issued by all applicable reviewers. For final approval, ensure the building plans match the approved DP regarding footprint, proposed height, and square footage, and that the downspout and structure drainage systems shown in the building plans are consistent with those depicted in the Development Package plan set. 2. COMMENT: Additional comments may be forthcoming on the next review based on responses to Zoning and other PDSD reviewer comments. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: 3. COMMENT: If applicable, updated commercial building permit per any development package updates. 4. COMMENT: Provide a detailed response letter with your submittal that clearly shows how you have addressed all Zoning comments. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home . Instructions for resubmittal - https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/old-pdfs/double-old/resubmittals.pdf If you have any questions about this transmittal, please contact jeffrey.cassidy@tucsonaz.gov The Unified Development Code (UDC) can be found at: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes/Zoning-Code . |
||
| 09/22/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |