Permit Number: TC-COM-0924-01869
Parcel: 117061910

Address:
11 S 6TH AV

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0924-01869
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/16/2024 Site Zoning APPROVED
12/16/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
12/02/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer (from previous submittal TUC9604001.093024)
Madeline Nelson
mnelson@safebuilt.com
Approved
Reason:
Date Completed : 10/15/2024 10:09:32 PM




Building(B) Reviewer
Janet Matz
jmatz@safebuilt.com
Approved with Comments
Reason:
Date Completed : 11/28/2024 1:14:13 AM
Provide a copy of the statement of Special Inspection Services forms that are completed, and signed and sealed by the project design engineer




Mechanical(M) Reviewer
Julio E. Gonzalez
julio@mtcinspectors.com
Approved
Reason:
Date Completed : 11/25/2024 6:35:20 PM





Electrical(E) Reviewer (from previous submittal TUC9604001.093024)
Ron Ross
rross@safebuilt.com
Approved with Comments
Reason:
Date Completed : 10/2/2024 11:29:19 AM
1. E4.1 has error in Load Summary (277/480V) which should be (120/208V). Correct loads in amps calculated.
2. E4.1 has error in Electrical Single Line Diagram short circuit label above Panel A which is shown as F2 when it should be F3.
3. E4.2 panel schedule for L2 shows panels C and D added to load, but Sheet E4.1 Single Line shows as Panels A and B added. Should correct/coordinate for construction set
4. E4.2 panel schedule for K1 shows panels A and B added to load, but Sheet E4.1 Single Line shows as Panels C and D added. Should correct/coordinate for construction set.





Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 11/28/2024 2:33:37 PM
Second Plumbing Review: comments 2 & 3 remain
Resolved_1). Plan Page P1.2: Missing Gas system Legnth. Add gas system legnth to correlate with the gas sizing table listed. -2018 IFGC 402.3
Unresolved-2). Plan Page P1.0: To many items connected to Hydromechanical Grease interceptor. Per Tucson Plbg Code
amendments only 4 items allowed to be connected to the hydromechanical grease interceptor. (Plans show 17 items in total new & existing see grease sizing table)
Unresolved-3). General: Plumbing plans missing Drinking fountain & mop sink that are listed on plan page G1.1. Show all the required plumbing fixtures & their illustrations to the plumbing plans. -2018 IPC 403.1 (still need to show locations of mop sink & existing bottle filler/drinking fountain)
12/05/2024 Fire New Construction REVIEW COMPLETED
11/22/2024 PDSD Application Completeness Express REVIEW COMPLETED