Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0826-01223
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/26/2026 Commercial Building Standard APPROVED
08/26/2026 Commercial Plumbing Standard APPROVED
08/28/2026 Site Zoning Standard APPROVED
08/26/2026 Water - PDSD Standard APPROVED
08/20/2026 Outdoor Lighting Standard NOT REQUIRED
08/06/2026 Site Engineering Standard NOT REQUIRED
08/28/2026 Bldg Permits - Post Review Express PENDING ASSIGNMENT
08/20/2026 Commercial Electrical Standard REQUIRES RESUBMIT Conductor is undersized per NEC 240.4(E)(8) 10 AWG Copper.
30 amperes max. Reference sheet E4, Panel H1, Circuit 8,10,12, DU-2 unit.
08/26/2026 Commercial Mechanical Standard REQUIRES RESUBMIT 1. Explain how the heating and cooling load calculations for CU-1 and CU-2 are able to justify the heating/cooling capacities of the specified variable refrigerant volume (VRV) split systems. Reference: Section C403.1.1 and C502.2.3, IECC 2024.
2. The new storage room (IT room?) is served by both a ductless split system heat pump (DCU-1/DHP-1) and a VRV split system (CU-1/FC-14). Clarify how this complies with Section C403.3.1, IECC 2024 (i.e., is this a standby or backup system?). Reference: C502.2.3, IECC 2024.

If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov.
08/26/2026 Fire New Construction Standard REVIEW COMPLETED
08/06/2026 PDSD Application Completeness Express REVIEW COMPLETED