Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0825-01540
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/08/2025 | Commercial Building Standard | APPROVED | |||
| 09/05/2025 | Site Zoning Standard | APPROVED | |||
| 08/21/2025 | Outdoor Lighting Standard | NOT REQUIRED | No modifications to the outdoor lighting. | ||
| 08/29/2025 | Site Engineering Standard | NOT REQUIRED | |||
| 09/08/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/27/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | Commercial Electrical Review TC-COM-0825-01540 (7394 S NEXUS RD TUCSON, AZ 85747) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2018 International Building Code (IBC), 2017 National Electrical Code (NEC). 1. Provide electrical load calculations, for the Main Services, Per NEC 220.40. 2. Provide an updated panel schedules, showing the circuits that are being modified, added or removed or existing. NEC arts;300 and 408.4. Include panel bus rating and A.I.C. rating. IBC 107.1. 3. Designate the circuit number on the electrical plans, that corresponds to the panel schedule, at the location of each existing, new or modified light fixture, receptacle, and equipment disconnect switch, NEC arts;300 and 408.4. IBC 107.1. Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov |
||
| 09/03/2025 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 08/15/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |