Permit Number: TC-COM-0824-01622
Parcel: 10509553A

Address:
4888 N STONE AV

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0824-01622
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
11/15/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
10/28/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Kimiyoshi Shimabukuro
kshimabukuro@safebuilt.com
Denied
Reason:
Date Completed : 10/24/2024 1:59:29 AM
1. Missing geotechnical investigation document prepared by Terracon, dated April 12, 2024 file no. 63245022 stated in sheet C1.1. (Closed)
2. Division 31 earthwork missing from specification, but scope shows site work and grading operations. (Closed)
3. Structural calculation design criteria is using building code 2018 IBC but code references is using 2021 IBC. (Closed)
4. Civil sheets show “Plan check only” but this is for construction permit. (Closed)
5. Sheet C7.1 – 8” masonry CMU wall is used but missing from specification Division 4 – “Masonry – Not Used.” Sheet
S1.2 detail 05 references freestanding masonry wall and footing. Updated specifications missing from resubmittal document.
6. Provide drawing details of concrete beam and pole footing embedded in soil mentioned in structural calculations. Cross reference details in plans. (Closed)
7. When an Intermediate Special Inspection Report is required, the Outside Review Agency is responsible for verification of the Special Inspectors. Applicants are provided with the following instructions: Cover sheet special inspection lists
post-install anchors and steel welding. Special Inspections Intermediate Certificate
A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. Part A & B need to be completed prior to Issuance.
Part C to be completed prior to final Inspection You may obtain the form at the following link:
https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Commercial-Permits#section-2
The Condition is added to the permit and then satisfied upon approval of the form.






Building(B) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 10/23/2024 7:00:38 PM





Mechanical(M) Reviewer (from previous submittal TUC9591001.082124)
Jorge Valido
jvalido@safebuilt.com
Approved with Comments
Reason:
Date Completed : 9/3/2024 4:00:08 PM
1. General - This Review is for Demo of specified areas on 1st and 2nd levels/floors. Central Plant Demo. Installation of Boilers, associated ducting, piping and electrical to Mechanical equipment shown on Mechanical plans. Buildout of
Demo areas require a new review.





Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Approved
Reason:
Date Completed : 10/23/2024 6:03:21 PM
1. EP601 PANEL SCHEDULES shows Panel HV2 voltage as 208V vs EPS701 Single Line shows as 480V. Correct where required. Addressed
2. EPS701 SINGLE LINE DIAGRAM – SHELL does not have transformer TLV2 is not shown in Transformer Schedule. Addressed
3. EPS701 SINGLE LINE DIAGRAM – SHELL should provide guidance for Keynote 11 by providing minimum cubic volume and bending radii. Electrical contractor may install something that fits, but not meet code. Addressed








Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 10/26/2024 2:32:45 PM
Second Plumbing Review: Site, Shell, Demo project Resolved-1). General: Need to address Building Plan review comment #1 so a complete plumbing review can be done. - 2018 IPC 403.1, 106.3.1
Resolved-2). Plan pages Ps1.6 & Ps3.1: Missing Shut off valves for the hose bibs. Add the required Hose bib shut off valves. -2018 IPC 606.2
Resolved-3). Plan Page Ps0.1 or spec manual: Missing piping material specs for water, sanitary & Gas. Add the required piping material specs. -2018 IPC 106.3.1, 605.4, 702, IFGC 403
11/05/2024 Site Engineering REQUIRES RESUBMIT TC-COM-0824-01622
4888 N STONE AV

Site engineering comments are as follows:
1. Development package, TD-DEV-0824-00238 must be approved before this building permit can be approved.

Ryan Insalaco
Email: ryan.insalaco@tucsonaz.gov
Phone: (520) 837-5351
11/15/2024 Site Zoning REQUIRES RESUBMIT FROM: PDSD Zoning Review

PROJECT: TC-COM-0824-01622 - TD-DEV-0824-00238
4888 N STONE AV. – C-1/C-2
Medical Service: Outpatient, excluding blood donor centers (2nd Review)

TRANSMITTAL DATE: November 15, 2024

Resubmit revised drawings detailed response letter, which states how all Zoning Review Section comments were addressed.

This site is located in the C-1/C-2 zone (UDC 4.7.20 & 4.7.21). Multifamily is a permitted uses in this zone (Table 4.8-4), subject to Use Specific Standards 4.9.4.O.2, 4.9.13.O and 4.9.13.O

1. Zoning has reviewed the building plans for compliance with Development Package (DP) TD-DEV-0824-00238 an although the plans appear to match until the DP is approved by all review agencies Zoning cannot approve this plan.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.
10/31/2024 Fire New Construction REVIEW COMPLETED
10/22/2024 PDSD Application Completeness REVIEW COMPLETED