Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0824-01622
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/18/2024 | Water - PDSD | APPROVED | |||
09/23/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
09/05/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Kimiyoshi Shimabukuro kshimabukuro@safebuilt.com Denied Reason: Date Completed : 8/23/2024 9:36:47 PM 1. Missing geotechnical investigation document prepared by Terracon, dated April 12, 2024 file no. 63245022 stated in sheet C1.1. 2. Division 31 earthwork missing from specification, but scope shows site work and grading operations. 3. Structural calculation design criteria is using building code 2018 IBC but code references is using 2021 IBC. 4. Civil sheets show “Plan check only” but this is for construction permit. 5. Sheet C7.1 – 8” masonry CMU wall is used but missing from specification Division 4 – “Masonry – Not Used.” Sheet S1.2 detail 05 references freestanding masonry wall and footing. 6. Provide drawing details of concrete beam and pole footing embedded in soil mentioned in structural calculations. Cross reference details in plans. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Denied Reason: Date Completed : 8/27/2024 5:34:11 PM 1. Provide a Building Code Data Legend on the Title Sheet. Include the following code information for each building proposed: ◦ Occupancy Classification(s) ◦ Description of Use ◦ Type of Construction ◦ Sprinklers: ◦ Stories ◦ Height ◦ Floor Area ◦ NOTE: It is understood that this is a demolition and exterior renovation project. The above information is required for permit issuance. ◦ General: Provide a basic egress plan indicating that egress and all exits are still operable along with emergency and exit lighting. Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved with Comments Reason: Date Completed : 9/3/2024 4:00:08 PM 1. General - This Review is for Demo of specified areas on 1st and 2nd levels/floors. Central Plant Demo. Installation of Boilers, associated ducting, piping and electrical to Mechanical equipment shown on Mechanical plans. Buildout of Demo areas require a new review. Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 8/26/2024 2:06:28 PM 1. EP601 PANEL SCHEDULES shows Panel HV2 voltage as 208V vs EPS701 Single Line shows as 480V. Correct where required. 2. EPS701 SINGLE LINE DIAGRAM – SHELL does not have transformer TLV2 is not shown in Transformer Schedule. 3. EPS701 SINGLE LINE DIAGRAM – SHELL should provide guidance for Keynote 11 by providing minimum cubic volume and bending radii. Electrical contractor may install something that fits, but not meet code. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 9/3/2024 10:01:07 PM First Plumbing Review: Site, Shell, Demo project 1). General: Need to address Building Plan review comment #1 so a complete plumbing review can be done. - 2018 IPC 403.1, 106.3.1 2). Plan pages Ps1.6 & Ps3.1: Missing Shut off valves for the hose bibs. Add the required Hose bib shut off valves. -2018 IPC 606.2 3). Plan Page Ps0.1 or spec manual: Missing piping material specs for water, sanitary & Gas. Add the required piping material specs. -2018 IPC 106.3.1, 605.4, 702, IFGC 403 |
||
09/19/2024 | Fire New Construction | REQUIRES RESUBMIT | Resolve all building comments. john.vincent@tucsonaz.gov 5203495581 |
||
09/23/2024 | Site Engineering | REQUIRES RESUBMIT | TD-DEV-0824-00238 must be approved before this building permit can be approved. Mike Ortiz michael.ortiz@tucsonaz.goc |
||
09/16/2024 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review PROJECT: TC-COM-0824-01622 - TD-DEV-0824-00238 4888 N STONE AV. – C-1/C-2 Medical Service: Outpatient, excluding blood donor centers (1st Review) TRANSMITTAL DATE: September 16, 2024 Resubmit revised drawings detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in the C-1/C-2 zone (UDC 4.7.20 & 4.7.21). Multifamily is a permitted uses in this zone (Table 4.8-4), subject to Use Specific Standards 4.9.4.O.2, 4.9.13.O and 4.9.13.O 1. As Development Package (DP) TD-DEV-1023-00428 has not yet completed it’s 1st review Zoning is not able to review the building plans for compliance with the DP and will review on the next submittal. Until the DP is approved by all review agencies Zoning cannot approve this plan. 2. The development package sheets provided in the building plan set either need to be the stamped, approved plans, or marked for reference only. If you elect to mark for reference only do not mark the utility plans and if you elect to remove the plans leave the utility plans in the so Plumbing can review. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
08/20/2024 | PDSD Application Completeness | REVIEW COMPLETED |